BIL - BHP Billiton Plc - Exploration and developme18 Apr 2012
BIL
BIBLT                                                                           
BIL - BHP Billiton Plc - Exploration and development report For the quarter     
ended 31 March 2012                                                             
BHP BILLITON PLC                                                                
SHARE CODE:         BIL                                                         
ISIN:               GB0000566504                                                
NEWS RELEASE                                                                    
18 April 2012                                                                   
11/12                                                                           
BHP BILLITON EXPLORATION AND DEVELOPMENT REPORT                                 
FOR THE QUARTER ENDED 31 MARCH 2012                                             
This report covers the Group`s exploration and development activities for the   
March 2012 quarter. Unless otherwise stated, BHP Billiton`s interest in the     
projects referred to in this report is 100 per cent and references to project   
schedules are based on calendar years.                                          
Development                                                                     
BHP Billiton`s commitment to developing its portfolio of high return growth     
projects, diversified by commodity, geography and market was further            
reinforced by the approval of additional investment in its world class Base     
Metals, Iron Ore and Petroleum businesses.                                      
During the March 2012 quarter, BHP Billiton announced approval of the US$2.2    
billion (BHP Billiton share) Escondida Organic Growth Project 1 (OGP1) which    
involves the replacement of an existing concentrator and allows access to       
valuable, higher grade ore. BHP Billiton also approved the US$414 million (BHP  
Billiton share) Escondida Oxide Leach Area Project (OLAP).                      
In addition, pre-commitment expenditure of US$779 million (BHP Billiton share)  
for the proposed Western Australia Iron Ore (WAIO) Outer Harbour development    
was approved. This funding will enable feasibility studies to progress, the     
procurement of long lead time items and for dredging to begin, subject to the   
necessary regulatory approvals.                                                 
On 11 April 2012, BHP Billiton also approved pre-commitment funding of US$708   
million (BHP Billiton share) for the Mad Dog Phase 2 project in the deepwater   
Gulf of Mexico which will facilitate detailed engineering and the procurement   
of long lead time items related to the hull, topsides and subsea equipment.     
The Worsley Efficiency & Growth project will no longer be reported in future    
Exploration and Development Reports as it achieved first production in the      
March 2012 quarter and is 98 per cent complete.                                 
BHP Billiton`s Onshore US drilling and development expenditure totalled US$2.2  
billion for the nine months ended March 2012.                                   
Project and    Share of   Initial   Production       Quarterly progress         
ownership      approved   productio capacity (100%)                             
              capex      n target                                               
              (US$m)     date                                                   
Petroleum                                                                       
projects                                                                        
Macedon        1,050      CY13      200 million      On schedule and budget.    
(Australia)                         cubic feet gas   The overall project is     
71.43% Gas                          per day.         57% complete.              
Bass Strait    900        CY12(a)   10,000 bpd       On revised schedule and    
Kipper                              condensate and   budget. The overall        
(Australia)                         processing       project is 92% complete.   
32.5% - 50%                         capacity of 80                              
Gas/Gas                             million cubic                               
Liquids                             feet gas per                                
                                   day.                                         
Bass Strait    1,350      CY13      11,000 bpd       On revised schedule and    
Turrum                              condensate and   budget. The overall        
(Australia)                         processing       project is 78% complete.   
50% Gas/Gas                         capacity of 200                             
Liquids                             million cubic                               
feet gas per                                 
                                   day.                                         
North West     850        CY13      2,500 million    On budget. Steady state    
Shelf North                         cubic feet gas   production remains on      
Rankin B Gas                        per day.         track for CY13. The        
Compression                                          overall project is 87%     
(Australia)                                          complete.                  
16.67% LNG                                                                      
North West     400        CY16      To maintain LNG  On schedule and budget.    
Shelf Greater                       plant throughput The overall project is 9%  
Western Flank-                      from the North   complete.                  
A (Australia)                       West Shelf                                  
16.67% LNG                          operations.                                 
Minerals                                                                        
projects                                                                        
Worsley        2,995      Q1 CY12   1.1 million tpa  First production was       
Efficiency &                        of additional    achieved in Q1 CY12 and    
Growth                              alumina.         ramp up is underway. The   
(Australia)                                          overall project is 98%     
86% Alumina                                          complete.                  
Antamina       435        Q1 CY12   Increases ore    Commissioning of the SAG   
Expansion                           processing       mill and first production  
(Peru) 33.75%                       capacity to      was achieved in Q1 CY12.   
Copper                              130,000 tpd.     The overall project is     
90% complete.               
Escondida Ore  319        Q2 CY12   The relocation   On schedule and budget.    
Access (Chile)                      of the in-pit    The overall project is     
57.5% Copper                        crushing and     85% complete.              
conveyor                                     
                                   infrastructure                               
                                   provides access                              
                                   to higher grade                              
ore.                                         
Escondida      2,207      H1 CY15   Replaces the Los Approval announced. See    
Organic Growth                      Colorados        News Release dated 14      
Project 1                           concentrator     February 2012.             
(Chile) 57.5%                       with a new                                  
Copper                              152,000 tpd                                 
                                   plant.                                       
Escondida      414        H1 CY14   New dynamic      Approval announced. See    
Oxide Leach                         leaching pad and News Release dated 14      
Area Project                        mineral handling February 2012.             
(Chile) 57.5%                       system.                                     
Copper                              Maintains oxide                             
leaching                                     
                                   capacity.                                    
EKATI Misery   323        CY15      Project consists On schedule and budget.    
Open Pit                            of a pushback of The overall project is     
Project                             the existing     22% complete.              
(Canada) 80%                        Misery open pit                             
Diamonds                            which was mined                             
                                   from 2001 to                                 
2005.                                        
WAIO Jimblebar 3,300(b)   Q1 CY14   Increases mining On schedule and budget.    
Mine Expansion                      and processing   The overall project is     
(Australia)                         capacity to 35   27% complete.              
96% Iron Ore                        million tpa with                            
                                   incremental                                  
                                   debottlenecking                              
                                   opportunities to                             
55 million tpa.                              
WAIO Port      1,900(b)   H2 CY12   Increases total  On schedule and budget.    
Hedland Inner                       inner harbour    The overall project is     
Harbour                             capacity to 220  49% complete.              
Expansion                           million tpa with                            
(Australia)                         debottlenecking                             
85% Iron Ore                        opportunities to                            
                                   240 million tpa.                             
WAIO Port      1,400(b)   H2 CY14   Optimises        On schedule and budget.    
Blending and                        resource and     The overall project is     
Rail Yard                           enhances         16% complete.              
Facilities                          efficiency                                  
(Australia)                         across the WAIO                             
85% Iron Ore                        supply chain.                               
WAIO Orebody   698        H2 CY12   Maintains iron   On schedule and budget.    
24 (Australia)                      ore production   The overall project is     
85% Iron Ore                        output from the  12% complete.              
                                   Newman Joint                                 
                                   Venture                                      
                                   operations.                                  
Samarco Fourth 1,750      H1 CY14   Increases iron   On schedule and budget.    
Pellet Plant                        ore pellet       The overall project is     
(Brazil) 50%                        production       30% complete.              
Iron Ore                            capacity by 8.3                             
million tpa to                               
                                   30.5 million                                 
                                   tpa.                                         
Daunia         800        CY13      Greenfield mine  On schedule and budget.    
(Australia)                         development with The overall project is     
50%                                 capacity to      40% complete.              
Metallurgical                       produce 4.5                                 
Coal                                million tpa of                              
export                                       
                                   metallurgical                                
                                   coal.                                        
Broadmeadow    450        CY13      Increases        On schedule and budget.    
Life Extension                      productive       The overall project is     
(Australia)                         capacity by 0.4  62% complete.              
50%                                 million tpa and                             
Metallurgical                       extends life of                             
Coal                                the mine by 21                              
                                   years.                                       
Hay Point      1,250(b)   CY14      Increases port   On schedule and budget.    
Stage Three                         capacity from 44 The overall project is     
Expansion                           million tpa to   40% complete.              
(Australia)                         55 million tpa                              
50%                                 and reduces                                 
Metallurgical                       storm                                       
Coal                                vulnerability.                              
Caval Ridge    2,100(b)   CY14      Greenfield mine  On schedule and budget.    
(Australia)                         development and  The overall project is     
50%                                 expansion of the 33% complete.              
Metallurgical                       Peak Downs Mine                             
Coal                                with capacity to                            
                                   produce 8.0                                  
                                   million tpa of                               
export                                       
                                   metallurgical                                
                                   coal.                                        
RX1 Project    400        H2 CY12   Increases run-of-On schedule and budget.    
(Australia)                         mine thermal     The overall project is     
100% Energy                         coal production  78% complete.              
Coal                                by approximately                            
                                   4 million tpa.                               
Cerrejon P40   437        CY13      Increases        On schedule and budget.    
Project                             saleable thermal The overall project is     
(Colombia)                          coal production  21% complete.              
33.3% Energy                        by 8 million tpa                            
Coal                                to approximately                            
                                   40 million tpa.                              
Newcastle      367        CY14      Increases total  On schedule and budget.    
Third Port                          coal terminal    The overall project is     
Project Stage                       capacity from 53 21% complete.              
3 (Australia)                       million tpa to                              
35.5% Energy                        66 million tpa.                             
Coal                                                                            
Minerals exploration                                                            
Greenfield exploration continued on copper targets in South America, nickel     
and copper targets in Australia, and iron ore and potash in a number of         
regions globally.                                                               
For the nine months ended March 2012, BHP Billiton spent US$785 million on      
minerals exploration, of which US$668 million was expensed.                     
Petroleum exploration                                                           
Exploration and appraisal wells drilled during the quarter or in the process    
of drilling as at 31 March 2012.                                                
Well             Location           BHP Billiton equity   Status                
Gunflint-3       Gulf of Mexico     11.2%                 Drilling ahead        
                MC948              (Noble operator)                             
Julong Centre    Brunei             22.5%                 Plugged and           
                Block CA-01        (Total operator)      abandoned              
                                                         Dry hole               
Julong East      Brunei             22.5%                 Hydrocarbons          
Block CA-01        (Total operator)      encountered            
                                                         Drilling ahead         
Jujur-1          Sabah Malaysia     60%                   Plugged and           
                Block N            (Operator)            abandoned              
Dry hole               
N. Scarborough   Offshore Western   100%                  Plugged and           
                Australia          (Operator)            abandoned              
                WA-346-P                                 Hydrocarbons           
encountered            
Tallaganda-1     Offshore Western   55%                   Hydrocarbons          
                Australia          (Operator)            encountered            
                WA-351-P                                 Drilling ahead         
Petroleum exploration expenditure for the nine months ended March 2012 was      
US$925 million, of which US$409 million was expensed. Our guidance for          
petroleum exploration expenditure for the 2012 financial year is US$1.4         
billion, including the Onshore US exploration program. Onshore US Permian       
Basin appraisal activities for the March 2012 quarter included the successful   
completion and testing of six wells with commercial rates.                      
This report, together with the Production Report, represents the Interim        
Management Statement for the purposes of the UK Listing Authority`s Disclosure  
and Transparency Rules. There have been no significant changes in the           
financial position of the Group in the quarter ended 31 March 2012.             
(a) Facilities ready for first production pending resolution of mercury         
content.                                                                        
(b) Excludes announced pre-commitment funding.                                  
****                                                                            
Further information on BHP Billiton can be found at: www.bhpbilliton.com        
Sponsor: Absa Capital (the investment banking division of Absa Bank Limited,    
affiliated with Barclays Capital)                                               
Media Relations                                                                 
Australia                                                                       
Antonios Papaspiropoulos                                                        
Tel: +61 3 9609 3830  Mobile: +61 477 325 803                                   
email: Antonios.Papaspiropoulos@bhpbilliton.com                                 
Kelly Quirke                                                                    
Tel: +61 3 9609 2896  Mobile: +61 429 966 312                                   
email: Kelly.Quirke@bhpbilliton.com                                             
Fiona Martin                                                                    
Tel: +61 3 9609 2211  Mobile: +61 427 777 908                                   
email: Fiona.Martin2@bhpbilliton.com                                            
United Kingdom                                                                  
Ruban Yogarajah                                                                 
Tel: +44 20 7802 4033  Mobile: +44 7827 082 022                                 
email: Ruban.Yogarajah@bhpbilliton.com                                          
Americas                                                                        
Jaryl Strong                                                                    
Tel:  +1 713 499 5548  Mobile: +1 281 222 6627                                  
email: Jaryl.Strong@bhpbilliton.com                                             
Investor Relations                                                              
Australia                                                                       
James Agar                                                                      
Tel: +61 3 9609 2222 Mobile: +61 467 807 064                                    
email: James.Agar@bhpbilliton.com                                               
Andrew Gunn                                                                     
Tel: +61 3 9609 3575  Mobile: +61 439 558 454                                   
email: Andrew.Gunn@bhpbilliton.com                                              
United Kingdom and South Africa                                                 
Brendan Harris                                                                  
Tel: +44 20 7802 4131  Mobile: +44 7990 527 726                                 
email: Brendan.Harris@bhpbilliton.com                                           
Tara Dines                                                                      
Tel: +44 20 7802 7113  Mobile: +44 7825 342 232                                 
Email: Tara.Dines@bhpbilliton.com                                               
Americas                                                                        
Scott Espenshade                                                                
Tel: +1 713 599 6431  Mobile: +1 713 208 8565                                   
email: Scott.Espenshade@bhpbilliton.com                                         
BHP Billiton Limited ABN 49 004 028 077                                         
Registered in Australia                                                         
Registered Office: 180 Lonsdale Street                                          
Melbourne Victoria 3000 Australia                                               
Tel +61 1300 55 4757 Fax +61 3 9609 3015                                        
BHP Billiton Plc Registration number 3196209                                    
Registered in England and Wales                                                 
Registered Office: Neathouse Place                                              
London SW1V 1BH United Kingdom                                                  
Tel +44 20 7802 4000 Fax +44 20 7802 4111                                       
Members of the BHP Billiton Group which is headquartered in Australia           
Date: 18/04/2012 07:06:00 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.