BIL - BHP Billiton Plc - BHP Billiton exploration19 Oct 2011
BIL
BIBLT                                                                           
BIL - BHP Billiton Plc - BHP Billiton exploration and development report for    
the quarter ended 30 September 2011                                             
BHP Billiton Plc                                                                
Share code:    BIL                                                              
ISIN:          GB0000566504                                                     
NEWS RELEASE                                                                    
19 October 2011                                                                 
30/11                                                                           
BHP BILLITON EXPLORATION AND DEVELOPMENT REPORT FOR THE QUARTER ENDED 30        
SEPTEMBER 2011                                                                  
This report covers the Group`s exploration and development activities for the   
September 2011 quarter. Unless otherwise stated, BHP Billiton`s interest in     
the projects referred to in this report is 100 per cent and references to       
project schedules are based on calendar years.                                  
Development                                                                     
Western Australia Iron Ore (WAIO) Rapid Growth Project 5 (RGP5) was completed   
on schedule during the September 2011 quarter and the ramp up of this well      
timed project is now underway. Subsequent expansions to 240 million tonnes      
per annum and beyond will leverage infrastructure installed as part of the      
RGP5 project scope and enable BHP Billiton to fully utilise its inner harbour   
capacity at Port Hedland. The North West Shelf CWLH Life Extension project      
(Australia) was also completed on 24 September 2011. These projects will not    
be reported in future Exploration and Development Reports.                      
During the September 2011 quarter, BHP Billiton continued to add to its         
approved pipeline of high return, growth projects diversified across            
commodity, geography and customer. Investments in energy coal totalling         
US$804 million (BHP Billiton share) will facilitate a further phase of          
expansion at the world class Cerrejon coal mine (Colombia) to approximately     
40 million tonnes per annum (100 per cent basis) and the third stage of         
development of the Newcastle Coal Infrastructure Group`s (NCIG) coal handling   
facility in Newcastle (Australia).                                              
Project and     Share of    Initial    Production       Quarterly progress      
ownership       approved    production capacity (100%)                          
              capex       target                                                
              (US$m)      date                                                  
Petroleum                                                                       
projects                                                                        
Macedon         1,050       CY13       200 million      On schedule and budget. 
(Australia)                          cubic feet gas   The overall project is    
71.43% Gas                           per day.         39% complete.             
Bass Strait     900         CY12 (a)   10,000 bpd       On revised schedule and 
Kipper                               condensate and   budget. The overall       
(Australia)                          processing       project is 82% complete.  
32.5% - 50%                          capacity of 80                             
Gas/Gas                              million cubic                              
Liquids                              feet gas per                               
                                    day.                                        
Bass Strait     1,350       CY13       11,000 bpd       On revised schedule and 
Turrum                               condensate and   budget. The overall       
(Australia)                          processing       project is 69% complete.  
50% Gas/Gas                          capacity of 200                            
Liquids                              million cubic                              
                                    feet gas per                                
                                    day.                                        
North West      245         CY11       Replacement      First production        
Shelf CWLH                           vessel with      achieved on 24 September  
Life Extension                       capacity of      2011.                     
(Australia)                          60,000 bpd oil.                            
16.67% Oil                                                                      
North West      850         CY13       2,500 million    On budget. Steady state 
Shelf North                          cubic feet gas   production remains on     
Rankin B Gas                         per day.         track for CY13. The       
Compression                                           overall project is 75%    
(Australia)                                           complete.                 
16.67% LNG                                                                      
Minerals                                                                        
projects                                                                        
Worsley         2,995       Q1 CY12    1.1 million tpa  On revised schedule and 
Efficiency &                         of additional    budget. The overall       
Growth                               alumina.         project is 84% complete.  
(Australia)                                                                     
86% Alumina                                                                     
Antamina        435         Q4 CY11    Increases ore    On schedule and budget. 
Expansion                            processing       The overall project is    
(Peru) 33.75%                        capacity to      68% complete.             
Copper                               130,000 tpd.                               
Escondida Ore   319         Q2 CY12    The relocation   On schedule and budget. 
Access (Chile)                       of the in-pit    The overall project is    
57.5% Copper                         crushing and     57% complete.             
conveyor                                    
                                    infrastructure                              
                                    provides access                             
                                    to higher grade                             
ore.                                        
EKATI Misery    323         CY15       Project consists On schedule and budget. 
Open Pit                             of a pushback of The overall project is    
Project                              the existing     12% complete.             
(Canada) 80%                         Misery open pit                            
Diamonds                             which was mined                            
                                    from 2001 to                                
                                    2005.                                       
WAIO RGP5       4,800       H2 CY11    Scope review     First production        
(Australia)                          completed and    achieved on schedule,     
85%Iron Ore                          integrated into  ramp up underway.         
                                    subsequent                                  
expansion                                   
                                    approvals that                              
                                    will increase                               
                                    WAIO capacity to                            
220 million tpa.                            
WAIO Jimblebar  3,300 (b)   Q1 CY14    Increases mining On schedule and budget. 
Mine Expansion                       and processing   The overall project is    
(Australia)                          capacity to 35   15% complete.             
96% Iron Ore                         million tpa with                           
                                    incremental                                 
                                    debottlenecking                             
                                    opportunities to                            
55 million tpa.                             
WAIO Port       1,900 (b)   H2 CY12    Increases total  On schedule and budget. 
Hedland Inner                        inner harbour    The overall project is    
Harbour                              capacity to 220  35% complete.             
Expansion                            million tpa with                           
(Australia)                          debottlenecking                            
85% Iron Ore                         opportunities to                           
                                    240 million tpa.                            
WAIO Port       1,400 (b)   H2 CY14    Optimises        On schedule and budget. 
Blending and                         resource and     The overall project is    
Rail Yard                            enhances         11% complete.             
Facilities                           efficiency                                 
(Australia)                          across the WAIO                            
85% Iron Ore                         supply chain.                              
Samarco Fourth  1,750       H1 CY14    Increases iron   On schedule and budget. 
Pellet Plant                         ore pellet       The overall project is    
(Brazil) 50%                         production       9% complete.              
Iron Ore                             capacity by 8.3                            
                                    million tpa to                              
                                    30.5 million                                
tpa.                                        
Daunia          800         CY13       Greenfield mine  On schedule and budget. 
(Australia)                          development with The overall project is    
50%                                  capacity to      18% complete.             
Metallurgical                        produce 4.5                                
Coal                                 million tpa of                             
                                    export                                      
                                    metallurgical                               
coal.                                       
Broadmeadow     450         CY13       Increases        On schedule and budget. 
Life Extension                       productive       The overall project is    
(Australia)                          capacity by 0.4  43% complete.             
50%                                  million tpa and                            
Metallurgical                        extends life of                            
Coal                                 the mine by 21                             
                                    years.                                      
Hay Point       1,250 (b)   CY14       Increases port   On schedule and budget. 
Stage Three                          capacity from 44 The overall project is    
Expansion                            million tpa to   31% complete.             
(Australia)                          55 million tpa                             
50%                                  and reduces                                
Metallurgical                        storm                                      
Coal                                 vulnerability.                             
RX1 Project     400         H2 CY13    Increases run-of-On schedule and budget. 
(Australia)                          mine thermal     The overall project is    
100% Energy                          coal production  44% complete.             
Coal                                 by approximately                           
                                    4 million tpa.                              
Cerrejon P40    437         CY13       Increases        Approval announced.  See
Project                              saleable thermal News Release dated 18     
(Colombia)                           coal production  August 2011.              
33.3% Energy                         by 8 million tpa                           
Coal                                 to approximately                           
                                    40 million tpa.                             
Newcastle       367         CY14       Increases total  Approval announced.  See
Third Port                           coal terminal    News Release dated 31     
Project Stage                        capacity from 53 August 2011.              
3 (Australia)                        million tpa to                             
35.5%Energy                          66 million tpa.                            
Coal                                                                            
Minerals exploration                                                            
Greenfield exploration continued on copper targets in South America, Mongolia   
and Zambia; nickel and copper targets in Australia; and diamond targets in      
Canada. Exploration for iron ore, potash and uranium was undertaken in a        
number of regions including Australia, Africa and the Americas.                 
For the quarter ended 30 September 2011, BHP Billiton spent US$255 million on   
minerals exploration, of which US$213 million was expensed.                     
Petroleum exploration                                                           
Exploration and appraisal wells drilled during the quarter or in the process    
of drilling as at 30 September 2011.                                            
Well          Location             BHP Billiton equity   Status                 
Deep Blue-1   Green Canyon Gulf of 31.875%               Drilling ahead         
Mexico               (Noble operator)                              
             GC 723                                                             
Mad Dog North-Green Canyon Gulf of 23.9%                 Hydrocarbons           
1             Mexico               (BP operator) (c)     encountered            
GC 738                                     See News Release        
                                                       dated 7 September        
                                                       2011                     
                                                       Drilling ahead           
Bao Dom May-1 Western Trough       50%                   Plugged and            
             Vietnam              (Operator)            abandoned               
             Block 28                                   Dry hole                
Argus-2       Browse Basin         40%                   Temporarily            
Australia            (Woodside operator)   abandoned               
             AC/RL 8                                                            
Jurjur-1      Sabah Malaysia       60%                   Temporarily            
             Block N              (Operator)            suspended for           
equipment repairs        
Julong Centre Brunei               22.5%                 Drilling ahead         
             Block CA-01          (Total operator)                              
Canteen North Trinidad and Tobago  45%                   Plugged and            
Block 2C             (Operator)            abandoned               
                                                       Hydrocarbons             
                                                       encountered              
Seraph-1      North West Shelf     16.67%                Drilling ahead         
Australia            (Woodside operator)                           
             WA-3-L                                                             
Petroleum exploration expenditure for the quarter ended 30 September 2011 was   
US$155 million, of which US$64 million was expensed. Our guidance for           
petroleum exploration expenditure for the 2012 financial year is US$1           
billion, excluding Onshore US exploration.                                      
This report, together with the Production Report, represents the Interim        
Management Statement for the purposes of the UK Listing Authority`s             
Disclosure and Transparency Rules. There have been no significant changes to    
the financial position of the Group in the quarter ended 30 September 2011,     
other than those arising from the Group`s previously announced acquisition of   
Petrohawk Energy Corporation that was completed during the period which         
affected the Group`s cash reserves, net debt and gearing levels.                
(a) Facilities ready for first production pending resolution of mercury         
content.                                                                        
(b) Excludes announced pre-commitment funding.                                  
(c) BHP Billiton is operator of the well.                                       
****                                                                            
Further information on BHP Billiton can be found at: www.bhpbilliton.com        
Sponsor: Absa Capital (the investment banking division of Absa Bank Limited,    
affiliated with Barclays Capital)                                               
Media Relations                                                                 
Australia                                                                       
Samantha Stevens                                                                
Tel: +61 3 9609 2898  Mobile: +61 400 693 915                                   
email: Samantha.Stevens@bhpbilliton.com                                         
Kelly Quirke                                                                    
Tel: +61 3 9609 2896  Mobile: +61 429 966 312                                   
email: Kelly.Quirke@bhpbilliton.com                                             
Fiona Martin                                                                    
Tel: +61 3 9609 2211  Mobile: +61 427 777 908                                   
email: Fiona.Martin2@bhpbilliton.com                                            
United Kingdom and Americas                                                     
Ruban Yogarajah                                                                 
Tel: US +1 713 966 2907 or UK +44 20 7802 4033                                  
Mobile: UK +44 7827 082 022                                                     
email: Ruban.Yogarajah@bhpbilliton.com                                          
Investor Relations                                                              
Australia                                                                       
James Agar                                                                      
Tel: +61 3 9609 2222 Mobile: +61 467 807 064                                    
email: James.Agar@bhpbilliton.com                                               
Andrew Gunn                                                                     
Tel: +61 3 9609 3575  Mobile: +61 439 558 454                                   
email: Andrew.Gunn@bhpbilliton.com                                              
United Kingdom and South Africa                                                 
Brendan Harris                                                                  
Tel: +44 20 7802 4131  Mobile: +61 437 134 814                                  
email: Brendan.Harris@bhpbilliton.com                                           
Americas                                                                        
Scott Espenshade                                                                
Tel: +1 713 599 6431  Mobile: +1 713 208 8565                                   
email: Scott.Espenshade@bhpbilliton.com                                         
BHP Billiton Limited ABN 49 004 028 077                                         
Registered in Australia                                                         
Registered Office: 180 Lonsdale Street                                          
Melbourne Victoria 3000 Australia                                               
Tel +61 1300 55 4757 Fax +61 3 9609 3015                                        
BHP Billiton Plc Registration number 3196209                                    
Registered in England and Wales                                                 
Registered Office: Neathouse Place                                              
London SW1V 1BH United Kingdom                                                  
Tel +44 20 7802 4000 Fax +44 20 7802 4111                                       
Members of the BHP Billiton Group which is headquartered in Australia           
Date: 19/10/2011 07:07:27 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.