BIL - BHP Billiton plc - BHP Billiton exploration20 Apr 2011
BIL
BIBLT                                                                           
BIL - BHP Billiton plc - BHP Billiton exploration and development report for    
the quarter ended 31 March 2011                                                 
BHP Billiton Plc                                                                
Share code: BIL                                                                 
ISIN: GB0000566504                                                              
News Release                                                                    
20 April 2011                                                                   
14/11                                                                           
BHP BILLITON EXPLORATION AND DEVELOPMENT REPORT FOR THE QUARTER ENDED 31 MARCH  
2011                                                                            
This report covers the Group`s exploration and development activities for the   
quarter ended 31 March 2011. Unless otherwise stated, BHP Billiton`s interest   
in the projects referred to in this report is 100 per cent and references to    
project schedules are based on calendar years.                                  
Development                                                                     
BHP Billiton approved major projects with a total investment value of US$9.8    
billion (BHP Billiton share) during the March 2011 quarter. The progression of  
these projects into execution forms a meaningful component of the company`s     
anticipated organic growth program that is expected to exceed US$80 billion     
over the five years to the end of the 2015 financial year.                      
At Western Australia Iron Ore (WAIO), a commitment was made to further expand   
capacity to in excess of 220 million tonnes per annum (mtpa). BHP Billiton      
also commenced the important expansion of its Metallurgical Coal business with  
the approval of the 4.5 mtpa Daunia mine, the Stage Three Expansion of the Hay  
Point Coal Terminal and the Broadmeadow Life Extension project. In addition,    
BHP Billiton approved the RX1 Project at Hunter Valley Energy Coal and the      
Escondida Ore Access Project (copper).                                          
BHP Billiton`s longer term growth potential was further emphasised by the       
progression of both the Olympic Dam Project (copper and uranium) and Jansen     
Potash Project into feasibility.                                                
The MAC20 Project (energy coal) was completed in the March 2011 quarter and     
delivered first coal ahead of schedule and on budget. This project will no      
longer be reported in future Exploration and Development Reports.               
Project And     Share Of  Initial     Production       Quarterly                
Ownership       Approved  Production  Capacity (100%)  Progress                 
Capex     Target Date                                            
               US$M                                                             
Petroleum                                                                       
Projects                                                                        
Macedon         1,050     CY13        200 million      On schedule and budget.  
(Australia)                           cubic feet gas   The overall project is   
71.43%                                per day          18% complete.            
Gas                                                                             
Angostura Gas   180       H1 CY11     280 million      On schedule and budget.  
Phase II                              cubic feet gas   Topsides commissioned    
(Trinidad and                         per day          and ready to deliver     
Tobago)                                                gas. The overall         
45%                                                    project is greater than  
Gas                                                    99% complete.            
Bass Strait     900       CY12(a)     10,000 bpd       On revised schedule and  
Kipper                                condensate and   budget. Pipelines        
(Australia)                           processing       installed and subsea     
32.5% - 50%                           capacity of 80   infrastructure           
Gas/Gas Liquids                       million cubic    installation in          
                                     feet gas per day progress. The overall     
project is 73%            
                                                      complete.                 
Bass Strait     1,350     CY13        11,000 bpd       On revised schedule and  
Turrum                                condensate and   budget. Topsides         
(Australia)                           processing       nearing completion with  
50%                                   capacity of 200  substructure             
Gas/Gas Liquids                       million cubic    installation imminent.   
                                     feet gas per day The overall project is    
60% complete.             
North West      245       CY11        Replacement      On schedule and budget.  
Shelf CWLH Life                       vessel with      Floating Production      
Extension                             capacity of      Storage and Offtake      
(Australia)                           60,000 bpd oil   (FPSO) conversion        
16.67%                                                 continues. Offshore      
Oil                                                    construction activity    
                                                      has commenced. The        
overall project is 89%    
                                                      complete.                 
North West      850       CY12        2,500 million    On schedule and budget.  
Shelf North                           cubic feet gas   The overall project is   
Rankin B Gas                          per day          65% complete.            
Compression                                                                     
(Australia)                                                                     
16.67%                                                                          
LNG                                                                             
Minerals                                                                        
Projects                                                                        
Worsley         1,900     H1 CY11     1.1 million tpa  Budget and schedule is   
Efficiency &                          of additional    under review.            
Growth                                alumina          Construction is 61%      
(Australia)                                            complete. The overall    
86%                                                    project is 70%           
Alumina                                                complete.                
Antamina        435       Q4 CY11     Increases ore    On schedule and budget.  
Expansion                             processing       Engineering is 99%       
(Peru)                                capacity to      complete. Construction   
33.75%                                130,000 tpd      is 40% complete. The     
Copper                                                 overall project is 49%   
                                                      complete.                 
Escondida Ore   319       Q2 CY12     The relocation   Approval announced. See  
Access (Chile)                        of the in-pit    News Release dated 30    
57.5%                                 crushing and     March 2011.              
Copper                                conveyor                                  
                                     infrastructure                             
provides access                            
                                     to higher grade                            
                                     ore                                        
WAIO RGP5       4,800     H2 CY11     Scope review     On schedule and budget   
(Australia)                           completed and    based on original        
85%                                   integrated into  scope. Engineering is    
Iron Ore                              subsequent       over 99% complete.       
                                     expansion        Construction is 94%       
approvals that   complete. The overall     
                                     will increase    project is 95%            
                                     WAIO capacity to complete.                 
                                     220 million tpa                            
WAIO Jimblebar  3,300(b)  Q1 CY14     Increases mining Approval announced. See  
Mine Expansion                        and processing   News Release dated 25    
(Australia)                           capacity to 35   March 2011.              
96%                                   million tpa with                          
Iron Ore                              incremental                               
                                     debottlenecking                            
                                     opportunities to                           
                                     55 million tpa                             
WAIO Port       1,900(b)  H2 CY12     Increases total  Approval announced. See  
Hedland Inner                         inner harbour    News Release dated 25    
Harbour                               capacity to 220  March 2011.              
Expansion                             million tpa with                          
(Australia)                           debottlenecking                           
85%                                   opportunities to                          
Iron Ore                              240 million tpa                           
WAIO Port       1,400(b)  H2 CY14     Optimises        Approval announced. See  
Blending and                          resource and     News Release dated 25    
Rail Yard                             enhances         March 2011.              
Facilities                            efficiency                                
(Australia)                           across the WAIO                           
85%                                   supply chain                              
Iron Ore                                                                        
Daunia          800       CY13        Greenfield mine  Approval announced. See  
(Australia)                           development with News Release dated 25    
50%                                   capacity to      March 2011.              
Metallurgical                         produce 4.5                               
Coal                                  million tpa of                            
                                     export                                     
metallurgical                              
                                     coal                                       
Broadmeadow     450       CY13        Increases        Approval announced. See  
Life Extension                        productive       News Release dated 25    
(Australia)                           capacity by 0.4  March 2011.              
50%                                   million tpa and                           
Metallurgical                         extends life of                           
Coal                                  the mine by 21                            
years                                      
Hay Point Stage 1,250(b)  CY14        Increases port   Approval announced. See  
Three Expansion                       capacity from 44 News Release dated 25    
(Australia)                           million tpa to   March 2011.              
50%                                   55 million tpa                            
Metallurgical                         and reduces                               
Coal                                  storm                                     
                                     vulnerability                              
MAC20 Project   260       H1 CY11     Increases        Project is complete.     
(Australia)                           saleable thermal First coal delivered     
100%                                  coal production  ahead of schedule and    
Energy Coal                           by approximately on budget.               
3.5 million tpa                            
RX1 Project     400       H2 CY13     Increases run-of-Approval announced. See  
(Australia)                           mine thermal     News Release dated 25    
100%                                  coal production  March 2011.              
Energy Coal                           by approximately                          
                                     4 million tpa                              
(a) Facilities ready for first production pending resolution of mercury         
content.                                                                        
(b) Excludes announced pre-commitment funding.                                  
Minerals Exploration                                                            
Grassroots exploration continued on copper targets in South America, Mongolia   
and Zambia; nickel and copper targets in Australia; manganese targets in        
Gabon; and diamond targets in Canada. Exploration for iron ore, coal, bauxite,  
potash and manganese was undertaken in a number of regions including            
Australia, Canada, South America and Africa.                                    
For the nine months ended 31 March 2011, BHP Billiton spent US$428 million on   
minerals exploration, of which US$356 million was expensed.                     
Petroleum Exploration                                                           
Exploration and appraisal wells drilled during the quarter or in the process    
of drilling as at 31 March 2011.                                                
Well          Location              BHP Billiton Equity    Status               
Deep Blue-1   Green Canyon Gulf of  31.875%                Temporarily          
             Mexico                (Noble operator)       suspended             
             GC 723                                      Hydrocarbons           
encountered            
Petroleum exploration expenditure for the nine months ended 31 March 2011 was   
US$247 million, of which US$199 million was expensed. Our petroleum             
exploration expenditure for the 2011 financial year is now expected to be less  
than US$600 million. The decrease is largely due to permitting delays in the    
Gulf of Mexico.                                                                 
This report, together with the Production Report, represents the Interim        
Management Statement for the purposes of the UK Listing Authority`s Disclosure  
and Transparency Rules. There have been no significant changes in the           
financial position of the Group in the quarter ended 31 March 2011.             
Further information on BHP Billiton can be found on our Internet site:          
www.bhpbilliton.com                                                             
Australia                                                                       
Brendan Harris, Investor Relations                                              
Tel: +61 3 9609 4323  Mobile: +61 437 134 814                                   
email: Brendan.Harris@bhpbilliton.com                                           
Samantha Stevens, Media Relations                                               
Tel: +61 3 9609 2898 Mobile: +61 400 693 915                                    
email: Samantha.Stevens@bhpbilliton.com                                         
Amanda Buckley, Media Relations                                                 
Tel: +61 3 9609 2209  Mobile: +61 419 801 349                                   
email: Amanda.Buckley@bhpbilliton.com                                           
Kelly Quirke, Media Relations                                                   
Tel: +61 3 9609 2896  Mobile: +61 429 966 312                                   
email: Kelly.Quirke@bhpbilliton.com                                             
Fiona Martin, Media Relations                                                   
Tel: +61 3 9609 2211  Mobile: +61 427 777 908                                   
email: Fiona.Martin2@bhpbilliton.com                                            
United Kingdom & South Africa                                                   
Andre Liebenberg, Investor Relations                                            
Tel: +44 20 7802 4131  Mobile: +44 7920 236 974                                 
email: Andre.Liebenberg@bhpbilliton.com                                         
United Kingdom & Americas                                                       
Ruban Yogarajah, Media Relations                                                
Tel: US +1 713 966 2907 or UK +44 20 7802 4033                                  
Mobile: UK +44 7827 082 022                                                     
email: Ruban.Yogarajah@bhpbilliton.com                                          
Americas                                                                        
Scott Espenshade, Investor Relations                                            
Tel: +1 713 599 6431   Mobile: +1 713 208 8565                                  
email: Scott.Espenshade@bhpbilliton.com                                         
BHP Billiton Limited ABN 49 004 028 077                                         
Registered in Australia                                                         
Registered Office: 180 Lonsdale Street                                          
Melbourne Victoria 3000 Australia                                               
Tel +61 1300 55 4757 Fax +61 3 9609 3015                                        
BHP Billiton Plc Registration number 3196209                                    
Registered in England and Wales                                                 
Registered Office: Neathouse Place                                              
London SW1V 1BH United Kingdom                                                  
Tel +44 20 7802 4000 Fax +44 20 7802 4111                                       
Members of the BHP Billiton group which is headquartered in Australia           
Date: 20/04/2011 07:06:01 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.