BIL - BHP Billiton Plc - BHP Billiton exploration20 Jan 2011
BIL
BIBLT                                                                           
BIL - BHP Billiton Plc - BHP Billiton exploration and development report for the
quarter ended 31 December 2010                                                  
BHP Billiton Plc                                                                
Share code:    BIL                                                              
ISIN:          GB0000566504                                                     
News Release                                                                    
20 January 2011                                                                 
03/11                                                                           
BHP BILLITON EXPLORATION AND DEVELOPMENT REPORT FOR THE QUARTER ENDED 31        
DECEMBER 2010                                                                   
This report covers the Group`s exploration and development activities for the   
quarter ended 31 December 2010. Unless otherwise stated, BHP Billiton`s interest
in the projects referred to in this report is 100 per cent and references to    
project schedules are based on calendar years.                                  
Development                                                                     
During the December 2010 quarter, a further US$570 million (BHP Billiton share) 
of capital expenditure was approved to underpin continued growth in Western     
Australia Iron Ore`s production profile. The investment expands on BHP          
Billiton`s earlier pre-commitment of US$1.73 billion (BHP Billiton share)       
announced in January 2010 and will facilitate the ongoing development of port,  
rail and Jimblebar mine infrastructure.                                         
Industry wide cost pressure is being experienced across a broad range of        
projects and reflects stronger producer currencies, particularly in Australia,  
and underlying inflation on raw material and labour costs.                      
Project And       Share Of   Initial    Production       Quarterly              
Ownership         Approved   Production Capacity (100%)  Progress               
                Capex      Target                                               
US$M       Date                                                 
Petroleum                                                                       
Projects                                                                        
Macedon           1,050      CY13       200 million      On schedule and budget.
(Australia)                            cubic feet gas   Drilling campaign       
71.43%                                 per day          completed. The overall  
Gas                                                     project is 14%          
                                                      complete.                 
Angostura Gas     180        H1 CY11    280 million      On schedule and budget.
Phase II                               cubic feet gas   Topsides installation   
(Trinidad and                          per day          completed. Hook-up and  
Tobago)                                                 commissioning           
45%                                                     progressing. The        
Gas                                                     overall project is 98%  
                                                      complete.                 
Bass Strait       900        CY12(a)    10,000 bpd       Schedule and budget    
Kipper                                 condensate and   review completed.       
(Australia)                            processing       Additional funding      
32.5% - 50%                            capacity of 80   approved. First phase   
Gas/Gas Liquids                        million cubic    of drilling completed.  
feet gas per     Mercury encountered in   
                                      day              reservoir with solution  
                                                      being managed             
                                                      separately. The overall   
project is 62%            
                                                      complete.                 
Bass Strait       1,350      CY13       11,000 bpd       Schedule and budget    
Turrum                                 condensate and   review completed.       
(Australia)                            processing       Additional funding      
50%                                   capacity of 200  approved. The overall    
Gas/Gas Liquids                        million cubic    project is 54%          
                                      feet gas per     complete.                
day                                       
North West Shelf  245        CY11       Replacement      On schedule and budget.
CWLH Life                              vessel with      Floating Production     
Extension                              capacity of      Storage and Offtake     
(Australia)                            60,000 bpd oil   (FPSO) conversion       
16.67%                                                  continues. The overall  
Oil                                                     project is 85%          
                                                      complete.                 
North West Shelf  850        CY12       2,500 million    On schedule and budget.
North Rankin B                         cubic feet gas   The overall project is  
Gas Compression                        per day          62% complete.           
(Australia)                                                                     
16.67%                                                                          
LNG                                                                             
Minerals Projects                                                               
Worsley           1,900      H1 CY11    1.1 million tpa  On schedule. Budget is 
Efficiency &                           of additional    under review.           
Growth                                 alumina          Construction is 46%     
(Australia)                                             complete. The overall   
86%                                                     project is 59%          
Alumina                                                 complete.               
Antamina          435        Q4 CY11    Increases ore    On schedule and budget.
Expansion (Peru)                       processing       Engineering is 91%      
33.75%                                 capacity to      complete. Construction  
Copper                                 130,000 tpd      is 32% complete. The    
                                                      overall project is 40%    
                                                      complete.                 
Iron Ore (Western 4,800      H2 CY11    50 million tpa   Engineering is 99%     
Australia)                             additional iron  complete. Construction  
RGP5                                   ore system       is 89% complete. The    
85%                                    capacity         overall project is 90%  
Iron Ore                                                complete, based on      
original scope. The       
                                                      scope of the iron ore     
                                                      development sequence      
                                                      continues to be           
reviewed.                 
MAC20 Project     260        H1 CY11    Increases        First production       
(Australia)                            saleable         achieved ahead of       
100%                                   thermal coal     schedule in October     
Energy Coal                            production by    2010. Ramp up underway. 
                                      approximately    The overall project is   
                                      3.5 million tpa  97% complete.            
(a) Facilities ready for first production pending resolution of mercury content.
Minerals Exploration                                                            
Grassroots exploration continued on copper targets in Chile and Zambia; nickel  
and copper targets in Australia; manganese targets in Gabon; and diamond targets
in Canada. Exploration for iron ore, coal, bauxite, potash and manganese was    
undertaken in a number of regions including Australia, Canada, South America and
Africa.                                                                         
For the half year ended 31 December 2010, BHP Billiton spent US$279 million on  
minerals exploration, of which US$228 million was expensed.                     
Petroleum Exploration                                                           
Exploration and appraisal wells drilled during the quarter or in the process of 
drilling as at 31 December 2010.                                                
Well          Location              BHP Billiton Equity    Status               
Deep Blue-1   Green Canyon Gulf of  31.875%                Temporarily suspended
             Mexico                (Noble operator)       Hydrocarbons          
             GC 723                                       encountered           
SE Longtom-1  Gippsland Basin       50%                    Plugged & abandoned  
Australia             (Exxon operator)       Hydrocarbons          
             VIC/RL09                                     encountered           
Yellowfin-1   Gippsland Basin       50%                    Plugged & abandoned  
             Australia             (Exxon operator)       Dry hole              
VIC/RL6                                                            
Petroleum exploration expenditure for the half year ended 31 December 2010 was  
US$173 million, of which US$135 million was expensed.                           
Further information on BHP Billiton can be found on our Internet site:          
www.bhpbilliton.com.                                                            
Australia                                                                       
Brendan Harris, Investor Relations                                              
Tel: +61 3 9609 4323  Mobile: +61 437 134 814                                   
email: Brendan.Harris@bhpbilliton.com                                           
Leng Lau, Investor Relations                                                    
Tel: +61 3 9609 4202  Mobile: +61 403 533 706                                   
email: Leng.Y.Lau@bhpbilliton.com                                               
Amanda Buckley, Media Relations                                                 
Tel: +61 3 9609 2209  Mobile: +61 419 801 349                                   
email: Amanda.Buckley@bhpbilliton.com                                           
Kelly Quirke, Media Relations                                                   
Tel: +61 3 9609 2896  Mobile: +61 429 966 312                                   
email: Kelly.Quirke@bhpbilliton.com                                             
Fiona Martin, Media Relations                                                   
Tel: +61 3 9609 2211  Mobile: +61 427 777 908                                   
email: Fiona.Martin2@bhpbilliton.com                                            
United Kingdom & South Africa                                                   
Andre Liebenberg, Investor Relations                                            
Tel: +44 20 7802 4131  Mobile: +44 7920 236 974                                 
email: Andre.Liebenberg@bhpbilliton.com                                         
United Kingdom & Americas                                                       
Ruban Yogarajah, Media Relations                                                
Tel: US +1 713 966 2907 or UK +44 20 7802 4033                                  
Mobile: UK +44 7827 082 022                                                     
email: Ruban.Yogarajah@bhpbilliton.com                                          
Americas                                                                        
Scott Espenshade, Investor Relations                                            
Tel: +1 713 599 6431   Mobile: +1 713 208 8565                                  
email: Scott.Espenshade@bhpbilliton.com                                         
BHP Billiton Limited ABN 49 004 028 077                                         
Registered in Australia                                                         
Registered Office: 180 Lonsdale Street                                          
Melbourne Victoria 3000 Australia                                               
Tel +61 1300 55 4757 Fax +61 3 9609 3015                                        
BHP Billiton Plc Registration number 3196209                                    
Registered in England and Wales                                                 
Registered Office: Neathouse Place                                              
London SW1V 1BH United Kingdom                                                  
Tel +44 20 7802 4000 Fax +44 20 7802 4111                                       
Members of the BHP Billiton group which is headquartered in Australia           
Date: 20/01/2011 07:09:02 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.