BIL - BHP Billiton exploration and development rep20 Oct 2010
BIL
BIBLT                                                                           
BIL - BHP Billiton exploration and development report for the quarter ended 30  
September 2010                                                                  
BHP Billiton Plc                                                                
Share code: BIL                                                                 
ISIN: GB0000566504                                                              
20 October 2010                                                                 
29/10                                                                           
NEWS RELEASE                                                                    
BHP BILLITON EXPLORATION AND DEVELOPMENT REPORT                                 
FOR THE QUARTER ENDED 30 SEPTEMBER 2010                                         
This report covers the Group`s exploration and development activities for the   
quarter ended 30 September 2010. Unless otherwise stated, BHP Billiton`s        
interest in the projects referred to in this report is 100 per cent and         
references to project schedules are based on calendar years. This report,       
together with the Production Report, represents the Interim Management Statement
for the purposes of the UK Listing Authority`s Disclosure and Transparency      
Rules. There have been no significant changes to the financial position of the  
Group in the quarter ended 30 September 2010.                                   
Development                                                                     
During the quarter, the Douglas-Middelburg Optimisation Project (energy coal)   
was completed and delivered first coal on schedule and budget. This project will
no longer be reported in future Exploration and Development Reports.            
The approval of the Macedon Project (gas), offshore Western Australia was       
announced on 24 September 2010                                                  
Project And          Share Of    Initial      Production     Quarterly Progress 
Ownership            Approved    Production   Capacity                          
                    Capex US$M  Target Date  (100%)                             
Petroleum Projects                                                              
Macedon              1,050       CY13         200 million    Approval           
(Australia)                                   cubic feet gas announced, see     
71.43%                                        per day        news release dated 
Gas                                                          24 September 2010. 
                                                            Drilling campaign   
                                                            commenced. The      
                                                            overall project is  
3% complete.        
Angostura Gas Phase  180         H1 CY11      280 million    On schedule and    
II (Trinidad and                              cubic feet gas budget. Topsides   
Tobago)                                       per day        fabrication        
45%                                                          completed and en   
Gas                                                          route to Trinidad. 
                                                            Installation        
                                                            campaign            
progressing. The    
                                                            overall project is  
                                                            74% complete.       
Bass Strait Kipper   500         CY11         10,000 bpd     Schedule and       
(Australia)                                   condensate and budget under       
32.5% - 50%                                   processing     review following   
Gas/Gas Liquids                               capacity of 80 advice from the    
                                             million cubic  operator.           
feet gas per                       
                                             day                                
Bass Strait Turrum   625         CY11         11,000 bpd     Schedule and       
(Australia)                                   condensate and budget under       
50%                                           processing     review following   
Gas/Gas Liquids                               capacity of    advice from the    
                                             200 million    operator.           
                                             cubic feet gas                     
per day                            
North West Shelf     245         CY11         Replacement    On schedule and    
CWLH Life Extension                           vessel with    budget. Floating   
(Australia)                                   capacity of    Production Storage 
16.67%                                        60,000 bpd oil and Offtake (FPSO) 
Oil                                                          conversion         
                                                            continues. The      
                                                            overall project is  
84% complete.       
North West Shelf     850         CY12         2,500 million  On schedule and    
North Rankin B Gas                            cubic feet gas budget. Jacket     
Compression                                   per day        fabrication        
(Australia)                                                  continuing ahead   
16.67%                                                       of schedule. The   
LNG                                                          overall project is 
                                                            56% complete.       
Minerals Projects                                                               
Worsley Efficiency & 1,900       H1 CY11      1.1 million    On schedule and    
Growth (Australia)                            tpa of         budget.            
86%                                           additional     Construction is    
Alumina                                       alumina        38% complete. The  
                                                            overall project is  
                                                            53% complete.       
Antamina Expansion   435         Q4 CY11      Increases ore  On schedule and    
(Peru)                                        processing     budget.            
33.75%                                        capacity to    Engineering is 82% 
Copper                                        130,000 tpd    complete.          
                                                            Construction is     
21% complete. The   
                                                            overall project is  
                                                            27% complete.       
Iron Ore (Western    4,800       H2 CY11      50 million tpa Engineering is 98% 
Australia)                                    additional     complete.          
RGP5                                          iron ore       Construction is    
85%                                           system         77% complete. The  
Iron Ore                                      capacity       overall project is 
79% complete.       
                                                            However, scope is   
                                                            currently being     
                                                            reviewed in order   
to confirm car      
                                                            dumping and ship    
                                                            loading             
                                                            requirements.       
Douglas-Middelburg   975         Mid CY10     10 million tpa Project is         
Optimisation (South                           export thermal complete. First    
Africa)                                       coal and 8.5   coal delivered on  
100%                                          million tpa    schedule and       
Energy Coal                                   domestic       budget.            
                                             thermal coal                       
                                             (sustains                          
                                             current                            
output)                            
MAC20 Project        260         H1 CY11      Increases      On schedule and    
(Australia)\                                  saleable       budget.            
100%                                          thermal coal   Engineering is     
Energy Coal                                   production by  complete.          
                                             approximately  Construction is     
                                             3.5 million    86% complete. The   
                                             tpa            overall project is  
92% complete.       
Minerals Exploration                                                            
Grassroots exploration continued on copper targets in Chile and Zambia; nickel  
targets in Australia; manganese targets in Gabon; and diamond targets in Canada.
Exploration for iron ore, coal, bauxite, potash and manganese was undertaken in 
a number of regions including Australia, Canada, South America and Africa.      
For the quarter ended 30 September 2010, BHP Billiton spent US$129 million on   
minerals exploration, of which US$106 million was expensed.                     
Petroleum Exploration                                                           
Exploration and appraisal wells drilled during the quarter or in the process of 
drilling as at 30 September 2010.                                               
Well         Location                  BHP Billiton       Status                
Equity                                     
Deep Blue-1  Green Canyon Gulf of      31.875%            Temporarily suspended 
            Mexico                    (Noble operator)   Hydrocarbons           
            GC 723                                      encountered             
Black Pearl- Exmouth Sub-basin         71.43%             Plugged & abandoned   
1            WA-42-L                   (operator)         Hydrocarbons          
                                                        encountered             
Toroa-1      East Falkland Basin       51%                Plugged & abandoned   
PL015_02                  (operator)         Dry hole               
Furness C-1  Exmouth Sub-basin         50%                Plugged & abandoned   
            WA-255-P                  (operator)         Dry hole               
Petroleum exploration expenditure for the quarter ended 30 September 2010 was   
US$74 million, of which US$56 million was expensed. Our guidance for petroleum  
exploration expenditure for the June 2011 financial year is unchanged at        
approximately US$900 million and is expected to be heavily weighted to the      
second half.                                                                    
****                                                                            
Further information on BHP Billiton can be found on our Internet site:          
www.bhpbilliton.com.                                                            
Australia                                                                       
Brendan Harris, Investor Relations                                              
Tel: +61 3 9609 4323 Mobile: +61 437 134 814                                    
email: Brendan.Harris@bhpbilliton.com                                           
Leng Lau, Investor Relations                                                    
Tel: +61 3 9609 4202  Mobile: +61 403 533 706                                   
email: Leng.Y.Lau@bhpbilliton.com                                               
Amanda Buckley, Media Relations                                                 
Tel: +61 3 9609 2209  Mobile: +61 419 801 349                                   
email: Amanda.Buckley@bhpbilliton.com                                           
Kelly Quirke, Media Relations                                                   
Tel: +61 3 9609 2896  Mobile: +61 429 966 312                                   
Email: Kelly.Quirke@bhpbilliton.com                                             
Fiona Martin, Media Relations                                                   
Tel: +61 3 9609 2211  Mobile: +61 427 777 908                                   
email: Fiona.Martin2@bhpbilliton.com                                            
United Kingdom & South Africa                                                   
Andre Liebenberg, Investor Relations                                            
Tel: +44 20 7802 4131  Mobile: +44 7920 236 974                                 
email: Andre.Liebenberg@bhpbilliton.com                                         
United Kingdom & Americas                                                       
Ruban Yogarajah, Media Relations                                                
Tel: +44 20 7802 4033                                                           
Mobile: UK +44 7827 082 022                                                     
email: Ruban.Yogarajah@bhpbilliton.com                                          
Americas                                                                        
Scott Espenshade, Investor Relations                                            
Tel: +1 713 599 6431  Mobile: +1 713 208 8565                                   
email: Scott.Espenshade@bhpbilliton.com                                         
BHP Billiton Limited ABN 49 004 028 077                                         
Registered in Australia                                                         
Registered Office: 180 Lonsdale Street                                          
Melbourne Victoria 3000 Australia                                               
Tel +61 1300 55 4757 Fax +61 3 9609 3015                                        
BHP Billiton Plc Registration number 3196209                                    
Registered in England and Wales                                                 
Registered Office: Neathouse Place                                              
London SW1V 1BH United Kingdom                                                  
Tel +44 20 7802 4000 Fax +44 20 7802 4111                                       
Members of the BHP Billiton group which is headquartered in Australia           
Date: 20/10/2010 07:06:01 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.