BIL - BHP Billiton exploration and development rep21 Jul 2010
BIL
BIBLT                                                                           
BIL - BHP Billiton exploration and development report for the quarter ended 30  
June 2010                                                                       
BHP Billiton Plc                                                                
Share Code: BIL                                                                 
Share: GB0000566504                                                             
News Release                                                                    
21 July 2010                                                                    
19/10                                                                           
BHP BILLITON EXPLORATION AND DEVELOPMENT REPORT FOR THE QUARTER ENDED 30 JUNE   
2010                                                                            
Development                                                                     
The Newcastle Third Port Project (energy coal) was completed in June 2010, ahead
of schedule and budget. This project will not be reported in future Exploration 
and Development reports.                                                        
During the year ended 30 June 2010 a further three projects achieved first      
production and two projects were sanctioned for development. The three          
commissioned projects were Western Australia Iron Ore Rapid Growth Project 4    
(iron ore), Klipspruit Expansion (energy coal) and Pyrenees (oil and gas). The  
sanctioned projects were MAC20 Project (energy coal) and Antamina Expansion     
(copper).                                                                       
In addition, US$2.4 billion of pre-commitment expenditure was approved to       
accelerate development of Western Australia Iron Ore Rapid Growth Project 6     
(iron ore), Caval Ridge and Hay Point Coal Terminal Stage 3 Expansion (both     
metallurgical coal) and the first stages of the Jansen Potash Project (potash). 
Project And       Share Of  Initial      Production         Quarterly           
Ownership         Approved  Production   Capacity (100%)    Progress            
                 Capex     Target Date                                          
US$M                                                           
Petroleum                                                                       
Projects                                                                        
Angostura Gas     180       H1 CY11      280 million cubic  On schedule and     
Phase II                                 feet gas per day   budget.             
(Trinidad and                                              Installation         
Tobago)                                                    campaign is          
45%                                                        ongoing.             
Gas                                                        Compression          
                                                         platform jacket        
                                                         installed. Topsides    
                                                         fabrication            
continues. The         
                                                         overall project is     
                                                         69% complete.          
Bass Strait       500       CY11         10,000 bpd         Schedule and budget 
Kipper                                   condensate and     under review        
(Australia)                              processing         following advice    
32.5% - 50%                              capacity of 80     from the operator.  
Gas/Gas Liquids                          million cubic                          
feet gas per day                         
Bass Strait       625       CY11         11,000 bpd         Schedule and budget 
Turrum                                   condensate and     under review        
(Australia)                              processing         following advice    
50%                                      capacity of 200    from the operator.  
Gas/Gas Liquids                          million cubic                          
                                       feet gas per day                         
North West Shelf  245       CY11         Replacement        On schedule and     
CWLH Life                                vessel with        budget. Floating    
Extension                                capacity of        Production Storage  
(Australia)                              60,000 bpd oil     and Offtake (FPSO)  
16.67%                                                     conversion           
Oil                                                        continues. The       
                                                         overall project is     
                                                         81% complete.          
North West Shelf  850       CY12         2,500 million      On schedule and     
North Rankin B                           cubic feet gas     budget. Jacket      
Gas Compression                          per day            fabrication         
(Australia)                                                continuing ahead of  
16.67%                                                     schedule. The        
LNG                                                        overall project is   
                                                         51% complete.          
Minerals Projects                                                               
Worsley           1,900     H1 CY11      1.1 million tpa    On schedule and     
Efficiency &                             of additional      budget.             
Growth                                   alumina            Construction is 27% 
(Australia)                                                complete. The        
86%                                                        overall project is   
Alumina                                                    44% complete.        
Antamina          435       Q4 CY11      Increases ore      On schedule and     
Expansion (Peru)                         processing         budget. Engineering 
33.75%                                   capacity to        is 75% complete.    
Copper                                   130,000 tpd        Construction is 7%  
                                                         complete. The          
                                                         overall project is     
                                                         18% complete.          
Iron Ore (Western 4,800     H2 CY11      50 million tpa     On schedule and     
Australia)                               additional iron    budget. Engineering 
RGP5                                     ore system         is 97% complete.    
85%                                      capacity           Construction is 61% 
Iron Ore                                                   complete. The        
                                                         overall project is     
                                                         64% complete.          
Douglas-          975       Mid CY10     10 million tpa     On schedule and     
Middelburg                               export thermal     budget.             
Optimisation                             coal and 8.5       Commissioning of    
(South Africa)                           million tpa        the coal processing 
100%                                     domestic thermal   plant is underway.  
Energy Coal                              coal (sustains     The overall project 
                                       current output)    is 98% complete.      
Newcastle Third   390       Mid CY10     30 million tpa     Project has been    
Port Project                             export coal        completed ahead of  
(Australia)                              loading facility   schedule and        
35.5%                                                      budget, with the     
Energy Coal                                                terminal becoming    
                                                         operational in June    
2010.                  
                                                           On schedule and      
                                                           budget. Engineering  
                                                           is complete.         
Increases          Construction is 75%  
                                        saleable thermal   complete. The        
MAC20 Project                            coal production    overall project is  
(Australia)                              by approximately   81% complete.       
100%                                     3.5 million tpa                        
Energy Coal       260       H1 CY11                                             
Minerals Exploration                                                            
Grassroots exploration continued on copper targets in Chile and Zambia; nickel  
targets in Australia; manganese targets in Gabon; and diamond targets in Canada.
Exploration for iron ore, coal, bauxite, potash and manganese was undertaken in 
a number of regions including Australia, Canada, South America, Russia and      
Africa.                                                                         
During the quarter, BHP Billiton confirmed the strength of its position in the  
Saskatchewan potash basin in Canada with the reporting of an in-situ Mineral    
Resource(1) of 3,370 million tonnes @ 25.4% K2O at its wholly-owned Jansen      
Potash Project. In addition, the Indonesian Coal Project (ICP) joint venture was
formed following Government approvals. PT Adaro Energy TBK has acquired a 25 per
cent interest in the ICP joint venture, with BHP Billiton holding the remaining 
75 per cent.                                                                    
For the year ended 30 June 2010, BHP Billiton spent US$516 million on minerals  
exploration, of which US$467 million was expensed. This includes US$73 million  
of exploration spend for potash in Saskatchewan, Canada.                        
(1) Competent Person`s Statement                                                
The statement of Mineral Resource being presented is based on information       
compiled by J.McElroy (MAusIMM) BHP Billiton, B.Nemeth (MAusIMM) BHP Billiton,  
and A. D. Mackintosh (APEGS) A.D.M Consulting and relates to Mineral Resource   
estimates as at 10 May 2010. A full statement of the Mineral Resource is        
provided in a BHP Billiton news release dated 7 June 2010. Competent Persons are
full time employees of BHP Billiton (unless otherwise stated), have sufficient  
experience relevant to the style of mineralisation and type of deposit under    
consideration and to the activity they are undertaking to qualify as a Competent
Person as defined in the JORC Code. All Competent Persons are members of either 
the Australian Institute of Mining & Metallurgy (AusIMM) or a Recognised        
Overseas Professional Organisation (ROPO). The Competent Persons consent to the 
inclusion in this report of the matters based on their information in the form  
and context in which it appears.                                                
Petroleum Exploration                                                           
Exploration and appraisal wells drilled during the quarter or in the process of 
drilling as at 30 June 2010.                                                    
Well       Location                  BHP Billiton        Status                 
Equity                                      
Deep Blue- Green Canyon Gulf of      31.875% BHP         Temporarily suspended  
1          Mexico                    Billiton            Hydrocarbons           
          GC 723                    (Noble operator)    encountered             
Double     Green Canyon Gulf of      70% BHP Billiton    Plugged & abandoned    
Mountain-1 Mexico                    (operator)          Dry hole               
          GC 555                                                                
Firefox-1  Green Canyon Gulf of      50% BHP Billiton    Plugged & abandoned    
Mexico                    (operator)          Dry hole                
          GC 817                                                                
Wolverine- Laurentian Basin Canada   45% BHP Billiton    Plugged & abandoned    
1          E.L. 1087R                (CoP operator)      Dry hole               
Bel Air-1  Liverpool Bay             46.1% BHP Billiton  Plugged & abandoned    
          110/13b                   (operator)          Dry hole                
Toroa-1    East Falkland Basin       51% BHP Billiton    Drilling ahead         
          PL015_02                  (operator)                                  
Furness C- Exmouth Sub-basin         50% BHP Billiton    Drilling ahead         
1          WA-255-P                  (operator)                                 
Petroleum exploration expenditure for the year ended 30 June 2010 was US$817    
million, of which US$563 million was expensed.                                  
****                                                                            
Further information on BHP Billiton can be found on our Internet site:          
www.bhpbilliton.com.                                                            
Australia                                                                       
Amanda Buckley, Media Relations                                                 
Tel: +61 3 9609 2209  Mobile: +61 419 801 349                                   
email: Amanda.Buckley@bhpbilliton.com                                           
Fiona Martin, Media Relations                                                   
Tel: +61 3 9609 2211  Mobile: +61 427 777 908                                   
email: Fiona.Martin2@bhpbilliton.com                                            
Leng Lau, Investor Relations                                                    
Tel: +61 3 9609 4202  Mobile: +61 403 533 706                                   
email: Leng.Y.Lau@bhpbilliton.com                                               
Brendan Harris, Investor Relations                                              
Tel: +61 3 9609 4323 Mobile: +61 437 134 814                                    
email: Brendan.Harris@bhpbilliton.com                                           
United Kingdom & South Africa                                                   
Andre Liebenberg, Investor Relations                                            
Tel: +44 20 7802 4131  Mobile: +44 7920 236 974                                 
email: Andre.Liebenberg@bhpbilliton.com                                         
Illtud Harri, Media Relations                                                   
Tel: +44 20 7802 4195  Mobile: +44 7920 237 246                                 
email: Illtud.Harri@bhpbilliton.com                                             
Americas                                                                        
Scott Espenshade, Investor Relations                                            
Tel: +1 713 599 6431   Mobile: +1 713 208 8565                                  
email: Scott.Espenshade@bhpbilliton.com                                         
Ruban Yogarajah, Media Relations                                                
Tel: US +1 713 966 2907 or UK +44 20 7802 4033                                  
Mobile: UK +44 7827 082 022                                                     
email: Ruban.Yogarajah@bhpbilliton.com                                          
BHP Billiton Limited ABN 49 004 028 077                                         
Registered in Australia                                                         
Registered Office: 180 Lonsdale Street                                          
Melbourne Victoria 3000 Australia                                               
Tel +61 1300 55 4757 Fax +61 3 9609 3015                                        
BHP Billiton Plc Registration number 3196209                                    
Registered in England and Wales                                                 
Registered Office: Neathouse Place                                              
London SW1V 1BH United Kingdom                                                  
Tel +44 20 7802 4000 Fax +44 20 7802 4111                                       
Members of the BHP Billiton group which is headquartered in Australia           
Date: 21/07/2010 07:06:02 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.