BIL - BHP Billiton Plc - BHP Billiton Exploration22 Jul 2009
BIL
BIBLT                                                                           
BIL - BHP Billiton Plc - BHP Billiton Exploration And Development Report For The
Quarter Ended 30 June 2009                                                      
BHP Billiton Plc                                                                
Share code:    BIL                                                              
ISIN:          GB0000566504                                                     
News Release                                                                    
22 July 2009                                                                    
14/09                                                                           
BHP BILLITON EXPLORATION AND DEVELOPMENT REPORT FOR THE QUARTER ENDED 30 JUNE   
2009                                                                            
This report covers the Group`s exploration and development activities for the   
quarter ended 30 June 2009. Unless otherwise stated, BHP Billiton`s interest in 
the projects referred to in this report is 100 percent and references to project
schedules are based on calendar years.                                          
Development                                                                     
First production was successfully achieved during the quarter at the Gemco      
Expansion Project in Australia (manganese) and the Atlantis North development in
the deep water Gulf of Mexico (oil and gas). Both projects were ahead of        
schedule and within budget. In addition, the Alumar Refinery Expansion in Brazil
(alumina) announced first production on 9 July. These projects will no longer be
reported in future Exploration and Development Reports.                         
During the year ended 30 June 2009 an additional four projects to those noted   
above achieved first production and four projects were sanctioned. The four     
commissioned projects, all oil and gas, were Neptune, North West Shelf Train 5, 
North West Shelf Angel and Shenzi. The sanctioned projects were the Bass Strait 
Turrum, Angostura Gas Phase II and the North West Shelf Cossack, Wanaea,        
Lambert, Hermes (CWLH) Life Extension projects (all oil and gas), as well as the
Western Australia Iron Ore Rapid Growth Project 5 (iron ore).                   
Project And   Share Of   Initial    Production     Quarterly                    
Ownership     Approved   Production Capacity       Progress                     
             Capex      Target     (100%)                                       
US$M       Date                                                    
Petroleum                                                                       
Projects                                                                        
Atlantis      185        H2 CY09    Tieback to     First production             
North (USA)                         Atlantis South achieved 5 June 2009,        
44%                                                ahead of schedule and        
Oil/Gas                                            within budget.               
Pyrenees      1,200      H1 CY10    96,000 barrels On schedule and              
(Australia)                         of oil and 60  budget. Floating             
71.43%                              million cubic  Production Storage and       
Oil/Gas                             feet gas per   Offtake (FPSO)               
                                   day            conversion continues.         
Final 3 of 15 tophole         
                                                  sections drilled and 2        
                                                  producers and 1               
                                                  injector well                 
completed.                    
                                                  Installation of subsea        
                                                  facilities continues.         
Angostura Gas 180        H1 CY11    280 million    On schedule and              
Phase II                            cubic feet gas budget. Platform             
(Trinidad and                       per day        fabrication continues.       
Tobago)                                                                         
45%                                                                             
Gas                                                                             
Bass Strait   500        CY11       10,000 bpd     On schedule and              
Kipper                              condensate and budget. West Tuna            
(Australia)                         processing     platform retrofit work       
32.5% - 50%                         capacity of 80 continuing.                  
Gas/Gas                             million cubic                               
Liquids                             feet gas per                                
                                   day                                          
Bass Strait   625        CY11       11,000 bpd     On schedule and              
Turrum                              condensate and budget. Commenced            
(Australia)                         processing     jacket and topsides          
50%                                 capacity of    fabrication ahead of         
Gas/Gas                             200 million    schedule.                    
Liquids                             cubic feet gas                              
                                   per day                                      
North West    245        CY11       Replacement    On schedule and              
Shelf CWLH                          vessel with    budget. Floating             
Life                                capacity of    Production Storage and       
Extension                           60,000 bpd oil Offtake (FPSO)               
(Australia)                                        conversion continues.        
16.67%                                                                          
Oil                                                                             
North West    850        CY12       2,500 million  On schedule and              
Shelf North                         cubic feet gas budget. Jacket               
Rankin B Gas                        per day        fabrication continuing       
Compression                                        ahead of schedule.           
(Australia)                                                                     
16.67%                                                                          
LNG                                                                             
Minerals                                                                        
Projects                                                                        
Alumar -      900        Q2 CY09    2 million tpa  First production             
Refinery                            of additional  announced. See News          
Expansion                           alumina        Release dated 9 July         
(Brazil)                                           2009.                        
36%                                                                             
Alumina                                                                         
Worsley       1,900      H1 CY11    1.1 million    On schedule and              
Efficiency &                        tpa of         budget. Engineering is       
Growth                              additional     75% complete and             
(Australia)                         alumina        construction has             
86%                                                commenced. Capital           
Alumina                                            expenditure profile is       
                                                  being managed to              
reflect changing              
                                                  market conditions.            
Iron Ore      1,850      H1 CY10    26 million tpa On schedule and              
(Western                            of additional  budget. Engineering is       
Australia)                          iron ore       99% complete and             
RGP4                                system         construction is over         
86.2%                               capacity       90% complete.                
Iron Ore                                                                        
Iron Ore      4,800      H2 CY11    50 million tpa On schedule and              
(Western                            additional     budget. Engineering is       
Australia)                          iron ore       currently 70%                
RGP5                                system         complete. Procurement        
85%                                 capacity       and contracting              
Iron Ore                                           activities are well          
                                                  advanced. Construction        
                                                  activities are                
continuing at all             
                                                  sites.                        
Gemco         110        H1 CY09    1 million tpa  First ore delivered          
(Australia)                         of additional  ahead of schedule and        
60%                                 manganese      within budget.               
Manganese                           concentrate                                 
Klipspruit    450        H2 CY09    Incremental    On schedule and              
(South                              1.8 million    budget. Commissioning        
Africa)                             tpa export     of the crushing stream       
100%                                thermal coal.  and coal processing          
Energy Coal                         Incremental    plant is progressing.        
                                   2.1 million    Project is 91%                
tpa domestic   complete.                     
                                   thermal coal                                 
Douglas-      975        Mid CY10   10 million tpa On schedule and              
Middelburg                          export thermal budget. Construction         
Optimisation                        coal and 8.5   activities are               
(South                              million tpa    progressing and first        
Africa)                             domestic       stacker reclaimer            
100%                                thermal coal   delivered. Steel             
Energy Coal                         (sustains      erection and coal            
                                   current        processing plant              
                                   output)        equipment installation        
                                                  remains on schedule.          
Project is 70%                
                                                  complete.                     
Newcastle     390        CY10       30 million tpa On schedule and              
Third Port                          export coal    budget. Stacker              
Project                             loading        reclaimer components         
(Australia)                         facility       delivered and                
35.5%                                              construction                 
Energy Coal                                        activities are               
progressing well.             
                                                  Project is greater            
                                                  than 63% complete.            
Minerals Exploration                                                            
BHP Billiton continues to identify and prioritise various exploration           
activities. All of the exploration activities are reviewed regularly to ensure  
that we are capturing value accretive opportunities for future development.     
For the year ended 30 June 2009, BHP Billiton spent US$695 million on minerals  
exploration, of which US$609 million was expensed. This includes US$94 million  
of exploration spend for potash in Saskatchewan, Canada.                        
Petroleum Exploration                                                           
Exploration and appraisal wells drilled during the quarter or in the process of 
drilling as at 30 June 2009.                                                    
Well        Location            BHP Billiton        Status                      
                               Equity                                           
Mad Dog     Green Canyon Gulf   23.9 % BHP          Hydrocarbons                
South-1     of Mexico GC 826    Billiton            encountered.                
                               (BHP Billiton       Completing                   
                               operator for this   sidetrack drilling           
                               well - BP operator  operations.                  
for all other                                    
                               activities)                                      
Brecknock-4 Browse Basin        8.33% BHP Billiton  Plugged and                 
           Western Australia   (Woodside           suspended.                   
WA-32-R             operator)           Dry hole.                    
Petroleum exploration expenditure for the year ended 30 June 2009 was US$548    
million, of which US$400 million was expensed.                                  
****                                                                            
Further information on BHP Billiton can be found on our website:                
www.bhpbilliton.com                                                             
Australia                                                                       
Samantha Evans, Media Relations                                                 
Tel: +61 3 9609 2898 Mobile: +61 400 693 915                                    
email: Samantha.Evans@bhpbilliton.com                                           
Peter Ogden, Media Relations                                                    
Tel: +61 3 9609 2812 Mobile: +61 428 599 190                                    
email: Peter.Ogden@bhpbilliton.com                                              
Kelly Quirke, Media Relations                                                   
Tel: +61 3 9609 2896 Mobile: +61 429 966 312                                    
email: Kelly.Quirke@bhpbilliton.com                                             
Leng Lau, Investor Relations                                                    
Tel: +61 3 9609 4202 Mobile: +61 403 533 706                                    
email: Leng.Y.Lau@bhpbilliton.com                                               
South Africa                                                                    
Bronwyn Wilkinson, Investor and Media Relations                                 
Tel: +44 20 7802 4015 Mobile: +44 7500 785 892                                  
email: Bronwyn.Wilkinson@bhpbilliton.com                                        
United Kingdom                                                                  
Andre Liebenberg, Investor Relations                                            
Tel: +44 20 7802 4131 Mobile: +44 7920 236 974                                  
email: Andre.Liebenberg@bhpbilliton.com                                         
Illtud Harri, Media Relations                                                   
Tel: +44 20 7802 4195 Mobile: +44 7920 237 246                                  
email: Illtud.Harri@bhpbilliton.com                                             
United States                                                                   
Scott Espenshade, Investor Relations                                            
Tel: +1 713 599 6431 Mobile: +1 713 208 8565                                    
email: Scott.Espenshade@bhpbilliton.com                                         
Ruban Yogarajah, Media Relations                                                
Tel: US +1 713 966 2907 or UK +44 20 7802 4033                                  
Mobile: UK +44 7827 082 022                                                     
email: Ruban.Yogarajah@bhpbilliton.com                                          
BHP Billiton Limited ABN 49 004 028 077                                         
Registered in Australia                                                         
Registered Office: 180 Lonsdale Street                                          
Melbourne Victoria 3000 Australia                                               
Tel +61 1300 55 4757 Fax +61 3 9609 3015                                        
BHP Billiton Plc Registration number 3196209                                    
Registered in England and Wales                                                 
Registered Office: Neathouse Place                                              
London SW1V 1BH United Kingdom                                                  
Tel +44 20 7802 4000 Fax +44 20 7802 4111                                       
A member of the BHP Billiton group which is headquartered in Australia          
Date: 22/07/2009 07:05:12 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.