BIL - Bhp Billiton Quarterly Report On Exploration23 Apr 2009
BIL
BIBLT                                                                           
BIL - Bhp Billiton Quarterly Report On Exploration And Development Activities   
                   Quarter Ended 31 March 2009                                  
BHP Billiton Plc                                                                
Share code: BIL                                                                 
ISIN: GB0000566504                                                              
News Release                                                                    
23 April 2009                                                                   
BHP BILLITON QUARTERLY REPORT ON EXPLORATION AND DEVELOPMENT ACTIVITIES         
QUARTER ENDED 31 MARCH 2009                                                     
This report covers the Group`s exploration and development activities for the   
quarter ended 31 March 2009. This report, together with the Production Report,  
represents the Interim Management Statement for the purposes of the UK Listing  
Authority`s Disclosure and Transparency Rules. Other than the issue of US$3.25  
billion in global bonds, as announced on 19 March 2009, there have been no      
significant changes to the financial position of the Group in the quarter ended 
31 March 2009. Unless otherwise stated, BHP Billiton`s interest in the projects 
referred to in this report is 100 percent and references to project schedules   
are based on calendar years.                                                    
Development                                                                     
During the quarter, Shenzi development in the deep water Gulf of Mexico (oil and
gas) delivered first production ahead of schedule within budget. This project   
will not be reported in future Exploration & Development Reports.               
Project and   Share of   Initial    Production    Quarterly Progress            
Ownership     Approved   Production Capacity                                    
             Capex      Target     (100%)                                       
             US$M       Date                                                    
Petroleum                                                                       
Projects                                                                        
Shenzi (USA)  1,940      Mid CY09   100,000       First production              
44%                                 barrels of    announced, ahead of           
Oil/Gas                             oil and 50    schedule and within           
million cubic budget. See News               
                                   feet gas per  Release dated 25 March         
                                   day           2009.                          
Atlantis      185        H2 CY09    Tieback to    On schedule and               
North (USA)                         Atlantis      budget. Manifold              
44%                                 South         fabrication                   
Oil/Gas                                           continuing.                   
Pyrenees      1,200      H1 CY10    96,000        On schedule and               
(Australia)                         barrels of    budget. Floating              
71.43%                              oil and 60    Production Storage and        
Oil/Gas                             million cubic Offtake (FPSO)                
                                   feet gas per  conversion continued.          
day           Drilling commenced as          
                                                 well as installation           
                                                 of subsea facilities.          
Angostura Gas 180        H1 CY11    280 million   On schedule and               
Phase II                            cubic feet    budget. Commenced             
(Trinidad and                       gas per day   platform fabrication.         
Tobago)                                                                         
45%                                                                             
Gas                                                                             
Bass Strait   500        CY11       10,000 bpd    On schedule and               
Kipper                              condensate    budget. West Tuna             
(Australia)                         and           platform retrofit work        
32.5% - 50%                         processing    continuing.                   
Gas/Gas                             capacity of                                 
Liquids                             80 million                                  
                                   cubic feet                                   
gas per day                                  
Bass Strait   625        CY11       11,000 bpd    On schedule and               
Turrum                              condensate    budget. Engineering           
(Australia)                         and           achieved to support           
50%                                 processing    procurement schedule.         
Gas/Gas                             capacity of                                 
Liquids                             200 million                                 
                                   cubic feet                                   
gas per day                                  
North West    245        CY11       Replacement   On schedule and               
Shelf CWLH                          vessel with   budget. Floating              
Life                                capacity of   Production Storage and        
Extension                           60,000 bpd    Offtake (FPSO)                
(Australia)                         oil           conversion commenced.         
16.67%                                                                          
Oil                                                                             
North West    850        CY12       2,500 million On schedule and               
Shelf North                         cubic feet    budget. Jacket                
Rankin B Gas                        gas per day   fabrication                   
Compression                                       continuing. Topsides          
(Australia)                                       design review                 
16.67%                                            milestone completed.          
LNG                                                                             
Minerals                                                                        
Projects                                                                        
Alumar -      900        Q2 CY09    2 million tpa On schedule and               
Refinery                            of additional revised budget.               
Expansion                           alumina       Engineering is                
(Brazil)                                          complete and                  
36%                                               procurement nearing           
Alumina                                           completion.                   
                                                 Construction is 90%            
complete with the              
                                                 project overall 95%            
                                                 complete.                      
Worsley       1,900      H1 CY11    1.1 million   Initial production            
Efficiency &                        tpa of        date and total project        
Growth                              additional    scope and budget              
(Australia)                         alumina       remain unchanged.             
86%                                               Engineering is 58%            
Alumina                                           complete and                  
                                                 construction has               
                                                 commenced. The timing          
                                                 of capital expenditure         
will be modified in            
                                                 line with our                  
                                                 disciplined cash flow          
                                                 management. The main           
component being the            
                                                 Marradong mine                 
                                                 development; which is          
                                                 expected to be                 
commissioned in 2012.          
Iron Ore      1,850      H1 CY10    26 million    On schedule and               
(Western                            tpa of        budget. Engineering is        
Australia)                          additional    over 95% complete and         
RGP4 86.2%                          iron ore      construction is               
Iron Ore                            system        nearing 80% complete.         
                                   capacity                                     
Iron Ore      4,800      H2 CY11    50 million    On schedule and               
(Western                            tpa           budget. Engineering is        
Australia)                          additional    currently 50%                 
RGP5 85%                            iron ore      complete, procurement         
Iron Ore                            system        and contracting               
capacity      activities are                 
                                                 advancing.                     
                                                 Construction                   
                                                 activities have                
commenced.                     
Gemco         110        H1 CY09    1 million tpa On schedule and budget        
(Australia)                         of additional in local currency. All        
60%                                 manganese     major components on           
Manganese                           concentrate   site in preparation           
                                                 for installation.              
                                                 Project is 77%                 
                                                 complete.                      
Klipspruit    450        H2 CY09    Incremental   On schedule and               
(South                              1.8 million   budget. First coal to         
Africa)                             tpa export    Run Of Mine stockpile         
100%                                thermal coal. achieved. Processing          
Energy Coal                         Incremental   plant and industrial          
                                   2.1 million   buildings progressing          
                                   tpa domestic  well. The project is           
                                   thermal coal  81% complete.                  
Douglas-      975        Mid CY10   10 million    On schedule and               
Middelburg                          tpa export    budget. Construction          
Optimisation                        thermal coal  activities are                
(South                              and 8.5       accelerating as               
Africa)                             million tpa   scheduled. Steel              
100%                                domestic      erection and coal             
Energy Coal                         thermal coal  processing plant              
                                   (sustains     equipment installation         
current       progressing. The               
                                   output)       project is 48%                 
                                                 complete.                      
Newcastle     390        CY10       30 million    On schedule and               
Third Port                          tpa export    budget. Wharf                 
Project                             coal loading  construction                  
(Australia)                         facility      progressing well with         
35.5%                                             delivery of stacker           
Energy Coal                                       reclaimers commenced.         
                                                 Project is greater             
                                                 than 50% complete.             
Minerals Exploration                                                            
BHP Billiton continues to identify and prioritise various exploration           
activities. All of the exploration activities are reviewed regularly to ensure  
that we are capturing value accretive opportunities for future development.     
Grassroots exploration continued on targets in Australia, Chile, Argentina,     
Zambia and Gabon; and on diamond targets in Canada. Exploration for iron ore,   
coal, bauxite and manganese was undertaken in a number of regions including     
Australia, South America, Russia and West Africa.                               
For the nine months ended 31 March 2009, BHP Billiton spent US$514 million on   
minerals exploration, of which US$460 million was expensed.                     
Petroleum Exploration                                                           
Exploration and appraisal wells drilled during the quarter or in the process of 
drilling as at 31 March 2009.                                                   
Location            BHP Billiton        Status                       
Well                            Equity                                          
Lambert-9   Dampier Sub-Basin   16.67% BHP          Plugged and                 
           Western Australia   Billiton            abandoned.                   
WA-16-L             (Woodside           Hydrocarbons                 
                               operator)           encountered.                 
Lady Nora-3 Dampier Sub-Basin   16.67% BHP          Plugged and                 
           Western Australia   Billiton            abandoned.                   
WA-28-P             (Woodside           Dry hole.                    
                               operator)                                        
Tidepole-2  Dampier Sub-Basin   16.67% BHP          Plugged and                 
           Western Australia   Billiton            abandoned.                   
WA-5-L              (Woodside           Hydrocarbons                 
                               operator)           encountered.                 
Torosa-5    Browse Basin        8.33% BHP           Plugged and                 
           Western Australia   Billiton            abandoned.                   
WA-30-R             (Woodside           Hydrocarbons                 
                               operator)           encountered.                 
Puma-4      Green Canyon Gulf   29.805% BHP         Temporarily                 
           of Mexico GC823     Billiton            abandoned.                   
(BP Operator)       Hydrocarbons                 
                                                  encountered.                  
Petroleum exploration expenditure for the nine months ended 31 March 2009 was   
US$351 million, of which US$242 million was expensed.                           
On March 18, BHP Billiton was the apparent successful high bidder on 28 blocks  
in the Central Gulf of Mexico Lease Sale 208, representing a total investment of
approximately US$50 million net to BHP Billiton. Final award of these blocks is 
subject to the usual process of confirmation by the Minerals Management Service 
(MMS) that BHP Billiton`s bids are acceptable.                                  
****                                                                            
Further information on BHP Billiton can be found on our website:                
www.bhpbilliton.com                                                             
Australia                                                                       
Samantha Evans, Media Relations                                                 
Tel: +61 3 9609 2898 Mobile: +61 400 693 915                                    
email: Samantha.Evans@bhpbilliton.com                                           
Peter Ogden, Media Relations                                                    
Tel: +61 3 9609 2812 Mobile: +61 428 599 190                                    
email: Peter.Ogden@bhpbilliton.com                                              
Kelly Quirke, Media Relations                                                   
Tel: +61 3 9609 2896 Mobile: +61 429 966 312                                    
email: Kelly.Quirke@bhpbilliton.com                                             
Leng Lau, Investor Relations                                                    
Tel: +61 3 9609 4202 Mobile: +61 403 533 706                                    
email: Leng.Y.Lau@bhpbilliton.com                                               
South Africa                                                                    
Bronwyn Wilkinson, Investor and Media Relations                                 
Tel: +44 20 7802 4015 Mobile: +44 7500 785 892                                  
email: Bronwyn.Wilkinson@bhpbilliton.com                                        
United Kingdom                                                                  
Andre Liebenberg, Investor Relations                                            
Tel: +44 20 7802 4131 Mobile: +44 7920 236 974                                  
email: Andre.Liebenberg@bhpbilliton.com                                         
Illtud Harri, Media Relations                                                   
Tel: +44 20 7802 4195 Mobile: +44 7920 237 246                                  
email: Illtud.Harri@bhpbilliton.com                                             
United States                                                                   
Scott Espenshade, Investor Relations                                            
Tel: +1 713 599 6431 Mobile: +1 713 208 8565                                    
email: Scott.Espenshade@bhpbilliton.com                                         
Ruban Yogarajah, Media Relations                                                
Tel: US +1 713 966 2907 or UK +44 20 7802 4033                                  
Mobile: UK +44 7827 082 022                                                     
email: Ruban.Yogarajah@bhpbilliton.com                                          
BHP Billiton Limited ABN 49 004 028 077                                         
Registered in Australia                                                         
Registered Office: 180 Lonsdale Street                                          
Melbourne Victoria 3000 Australia                                               
Tel +61 1300 55 4757 Fax +61 3 9609 3015                                        
BHP Billiton Plc Registration number 3196209                                    
Registered in England and Wales                                                 
Registered Office: Neathouse Place                                              
London SW1V 1BH United Kingdom                                                  
Tel +44 20 7802 4000 Fax +44 20 7802 4111                                       
A member of the BHP Billiton group which is headquartered in Australia          
Date: 23/04/2009 08:29:16 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.