BIL - BHP Billiton Plc - Quarterly report on explo21 Jan 2009
BIL
BIBLT                                                                           
BIL - BHP Billiton Plc - Quarterly report on exploration and development        
activities quarter ended 31 December 2008                                       
BHP Billiton Plc                                                                
Share Code:   BIL                                                               
ISIN:   GB0000566504                                                            
News Release                                                                    
21 January 2009                                                                 
03/09                                                                           
BHP BILLITON QUARTERLY REPORT ON EXPLORATION AND DEVELOPMENT ACTIVITIES         
QUARTER ENDED 31 DECEMBER 2008                                                  
DEVELOPMENT                                                                     
BHP Billiton`s strong balance sheet allows us to invest through the cycle with a
highly disciplined and value-focused approach.                                  
Highlighting our commitment to value accretive longer term growth, we sanctioned
two projects during the quarter, being the Western Australia Iron Ore Rapid     
Growth Project 5 (RGP5), and the North West Shelf Cossack, Wanaea, Lambert,     
Hermes (CWLH) Life Extension projects.                                          
PROJECT AND     SHARE OF   INITIAL     PRODUCTION   QUARTERLY PROGRESS          
OWNERSHIP       APPROVED   PRODUCTION  CAPACITY                                 
CAPEX      TARGET      (100%)                                    
               US$M       DATE                                                  
                                                                                
Petroleum                                                                       
Projects                                                                        
Shenzi (USA)    1,940      Mid CY09    100,000      Ahead of schedule and       
44%                                    barrels of   on budget. Hook-up and      
Oil/Gas                                oil and 50   commissioning               
million      continuing. Six wells        
                                      cubic feet   drilled and completed.       
                                      gas per day                               
Atlantis North  185        H2 CY09     Tieback to   On schedule and budget.     
(USA)                                  Atlantis     Manifold fabrication        
44%                                    South        continuing.                 
Oil/Gas                                                                         
Pyrenees        1,200      H1 CY10     96,000       On schedule and budget.     
(Australia)                            barrels of   Subsea hardware             
71.43%                                 oil and 60   delivery commenced and      
Oil/Gas                                million      Floating Production         
                                      cubic feet   Storage and Offtake          
gas per day  (FPSO) conversion            
                                                   continues.                   
Angostura Gas   180        H1 CY11     280 million  On schedule and budget.     
Phase II                               cubic feet   Awarded transportation      
(Trinidad and                          gas per day  and installation            
Tobago)                                             contract.  Executed         
45%                                                 National Gas Company        
Gas                                                 Interconnection             
Agreement.                   
Bass Strait     500        CY11        10,000 bpd   On schedule and budget.     
Kipper                                 condensate   Drilling rig secured.       
(Australia)                            and          Detailed engineering        
32.5% - 50%                            processing   progressing and             
Gas/Gas                                capacity of  commenced West Tuna         
Liquids                                80 million   platform retrofit work.     
                                      cubic feet                                
gas per day                               
Bass Strait     625        CY11        11,000 bpd   On schedule and budget.     
Turrum                                 condensate   Engineering and             
(Australia)                            and          procurement                 
50%                                    processing   progressing.                
Gas/Gas                                capacity of                              
Liquids                                200 million                              
                                      cubic feet                                
gas per day                               
North West      245        CY11        Replacement  The project was             
Shelf CWLH                             vessel with  sanctioned during the       
Life Extension                         capacity of  quarter. See News           
(Australia)                            60,000 bpd   Release dated 3             
16.67%                                 oil          December 2008.              
Oil                                                                             
North West      850        CY12        2,500        On schedule and budget.     
Shelf North                            million      Detailed engineering        
Rankin B Gas                           cubic feet   and procurement well        
Compression                            gas per day  advanced. Jacket            
(Australia)                                         fabrication commenced.      
16.67%                                                                          
LNG                                                                             
                                                                                
Minerals                                                                        
Projects                                                                        
Alumar -        900        Q2 CY09     2 million    On schedule and revised     
Refinery                               tpa of       budget. Engineering is      
Expansion                              additional   complete and                
(Brazil) 36%                           alumina      procurement well            
Alumina                                             advanced. Construction      
                                                   is 82% complete with         
                                                   the project overall 92%      
complete.                    
Worsley         1,900      H1 CY11     1.1 million  On schedule and budget.     
Efficiency &                           tpa of       Engineering is 49%          
Growth                                 additional   complete and                
(Australia)                            alumina      construction camp now       
86%                                                 operational.                
Alumina                                                                         
Iron Ore        1,850      H1 CY10     26 million   On schedule and budget.     
(Western                               tpa          Engineering is now over     
Australia)                             additional   95% complete and            
RGP4                                   iron ore     construction is nearing     
86.2%                                  system       70% complete.               
Iron Ore                               capacity                                 
Iron Ore        4,800      H2 CY11     50 million   The project was             
(Western                               tpa          sanctioned during the       
Australia)                             additional   quarter. See News           
RGP5                                   iron ore     Release dated 25            
85%                                    system       November 2008.              
Iron Ore                               capacity     Preliminary engineering     
                                                   and construction             
activities have              
                                                   commenced.                   
Gemco           110        H1 CY09     1 million    On schedule and budget      
(Australia)                            tpa of       in local currency.          
60%                                    additional   Cyclone tower               
Manganese                              manganese    operational and             
                                      concentrate  remainder of                 
                                                   installation activities      
progressing well.            
                                                   Project is 77%               
                                                   complete.                    
Klipspruit      450        H2 CY09     Incremental  On schedule and budget.     
(South Africa)                         1.8 million  Earthworks and civil        
100%                                   tpa export   and mechanical              
Energy Coal                            thermal      construction                
                                      coal         progressing well. The        
Incremental  project is 70% complete      
                                      2.1 million  with detailed                
                                      tpa          commission planning          
                                      domestic     commenced.                   
thermal                                   
                                      coal                                      
Douglas-        975        Mid CY10    10 million   On schedule and budget.     
Middelburg                             tpa export   Construction activities     
Optimisation                           thermal      are progressing well        
(South Africa)                         coal and     with steel erection         
100%                                   8.5 million  commencing as               
Energy Coal                            tpa          scheduled. The project      
domestic     is 34% complete.             
                                      thermal                                   
                                      coal                                      
                                      (sustains                                 
current                                   
                                      output)                                   
Newcastle       390        CY10        30 million   On schedule and budget.     
Third Port                             tpa export   Project is over 35%         
Project                                coal         complete.                   
(Australia)                            loading                                  
35.5%                                  facility                                 
Energy Coal                                                                     
MINERALS EXPLORATION                                                            
BHP Billiton continues to identify and prioritise various exploration           
activities. All of the exploration activities are reviewed regularly to ensure  
that we are capturing value accretive opportunities for future development.     
Selection study work on the proposed Olympic Dam Expansion (Australia) is       
effectively complete. A Draft Environmental Impact Statement (EIS) based on the 
five stage project configuration has been provided to the Federal, South        
Australian and Northern Territory Governments for a compliance review, with the 
intention that it be released for public comment during the first half of       
calendar year 2009. Pending government approvals for the EIS and consistent with
the prevailing economic circumstances, project activity will be scaled back to  
that necessary to support the approvals process and the study of a number of    
mining and processing technology options. Olympic Dam Expansion expenditure for 
the six months ended 31 December 2008 was US$112 million, of which US$29 million
was capitalised.                                                                
Grassroots exploration continued on targets in Australia, Chile, Argentina,     
Zambia and the Democratic Republic of Congo (DRC); and on diamond targets in    
Canada. Exploration for iron ore, coal, bauxite and manganese was undertaken in 
a number of regions including Australia, South America, Russia and West Africa. 
For the six months ended 31 December 2008, BHP Billiton spent US$357 million on 
minerals exploration, of which US$313 million was expensed.                     
PETROLEUM EXPLORATION                                                           
Exploration and appraisal wells drilled during the quarter or in the process of 
drilling as at 31 December 2008.                                                
WELL             LOCATION           BHP BILLITON EQUITY  STATUS                 
Lambert-8        Dampier Sub-Basin  16.67% BHP Billiton  Plugged and            
                Western Australia  (Woodside operator)  abandoned.              
                WA-16-L                                 Hydrocarbons            
encountered.            
Lambert West     Dampier Sub-Basin  16.67% BHP Billiton  Plugged and            
                Western Australia  (Woodside operator)  abandoned.              
                WA-16-L                                 Hydrocarbons            
encountered.            
Lady Nora-2      Dampier Sub-Basin  16.67% BHP Billiton  Plugged and            
                Western Australia  (Woodside operator)  abandoned.              
                WA-28-P                                 Hydrocarbons            
encountered.            
Nereus-1         Dampier Sub-Basin  16.67% BHP Billiton  Plugged and            
                Western Australia  (Woodside operator)  abandoned. Dry          
                WA-28-P                                 hole.                   
Tidepole-2       Dampier Sub-Basin  16.67% BHP Billiton  Drilling ahead.        
                Western Australia  (Woodside operator)                          
                WA-5-L                                                          
Torosa-5         Browse Basin       8.33% BHP Billiton   Plugging and           
Western Australia  (Woodside operator)  abandoning.             
                WA-30-R                                 Hydrocarbons            
                                                        encountered.            
Puma-4           Green Canyon       29.805% BHP          Drilling ahead.        
Gulf of Mexico     Billiton                                     
                GC823-2            (BP Operator)                                
                                                                                
Shenzi-8         Green Canyon       44% BHP Billiton,    Hydrocarbons           
Gulf of Mexico     operator             encountered.            
                GC610                                   Suspended.              
Petroleum exploration expenditure for the six months ended 31 December 2008 was 
US$263 million, of which US$183 million was expensed                            
****                                                                            
Further information on BHP Billiton can be found on our website:                
www.bhpbilliton.com                                                             
Australia                                                                       
Samantha Evans, Media Relations                                                 
Tel: +61 3 9609 2898 Mobile: +61 400 693 915                                    
email: Samantha.Evans@bhpbilliton.com                                           
Peter Ogden, Media Relations                                                    
Tel: +61 3 9609 2812 Mobile: +61 428 599 190                                    
email: Peter.Ogden@bhpbilliton.com                                              
Kelly Quirke, Media Relations                                                   
Tel:   +61 3 9609 2896 Mobile: +61 429 966 312                                  
email: Kelly.Quirke@bhpbilliton.com                                             
Leng Lau, Investor Relations                                                    
Tel:   +61 3 9609 4202 Mobile: +61 403 533 706                                  
email: Leng.Y.Lau@bhpbilliton.com                                               
United Kingdom & South Africa                                                   
Andre Liebenberg, Investor Relations                                            
Tel:   +44 20 7802 4131 Mobile: +44 7920 236 974                                
email: Andre.Liebenberg@bhpbilliton.com                                         
Illtud Harri, Media Relations                                                   
Tel:   +44 20 7802 4195 Mobile: +44 7920 237 246                                
email: Illtud.Harri@bhpbilliton.com                                             
United States                                                                   
Scott Espenshade, Investor Relations                                            
Tel:   +1 713 599 6431 Mobile: +1 713 208 8565                                  
email: Scott.Espenshade@bhpbilliton.com                                         
Ruban Yogarajah, Media Relations                                                
Tel:    US +1 713 966 2907 or UK +44 20 7802 4033                               
Mobile: UK +44 7827 082 022                                                     
email:  Ruban.Yogarajah@bhpbilliton.com                                         
BHP Billiton Limited ABN 49 004 028 077                                         
Registered in Australia                                                         
Registered Office: 180 Lonsdale Street                                          
Melbourne Victoria 3000 Australia                                               
Tel +61 1300 55 4757 Fax +61 3 9609 3015                                        
BHP Billiton Plc Registration number 3196209                                    
Registered in England and Wales                                                 
Registered Office: Neathouse Place                                              
London SW1V 1BH United Kingdom                                                  
Tel +44 20 7802 4000 Fax +44 20 7802 4111                                       
A member of the BHP Billiton group which is headquartered in Australia          
Date: 21/01/2009 07:29:02 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.