BIL - BHP Billiton Quarterly Report On Exploration22 Oct 2008
BIL
BIBLT                                                                           
BIL - BHP Billiton Quarterly Report On Exploration And Development Activities   
                   Quarter Ended 30 September 2008                              
BHP Billiton Plc                                                                
Share code: BIL                                                                 
ISIN: GB0000566504                                                              
22 October 2008                                                                 
Number 35/08                                                                    
BHP BILLITON QUARTERLY REPORT ON EXPLORATION AND DEVELOPMENT ACTIVITIES QUARTER 
ENDED 30 SEPTEMBER 2008                                                         
This report covers the Group`s exploration and development activities for the   
quarter ended 30 September 2008. This report, together with the Production      
Report, represents the Interim Management Statement for the purposes of the UK  
Listing Authority`s Disclosure and Transparency Rules.  There have been no      
significant changes to the financial position of the Group in the quarter ended 
30 September 2008. Unless otherwise stated, BHP Billiton`s interest in the      
projects referred to in this report is 100 per cent and references to project   
schedules are based on calendar years.                                          
DEVELOPMENT                                                                     
First production was successfully achieved during the quarter at Neptune and    
North West Shelf Train 5 (both petroleum). In addition, North West Shelf Angel  
(petroleum) delivered first production on 3 October 2008. These projects will   
not be reported in future Exploration and Development Reports.                  
During the quarter, we sanctioned two gas projects - Bass Strait Turrum and     
Angostura Gas Phase II. Atlantis North is now also detailed in the report.      
PROJECT AND     SHARE OF   INITIAL     PRODUCTION QUARTERLY PROGRESS            
OWNERSHIP       APPROVED   PRODUCTION  CAPACITY                                 
               CAPEX      TARGET      (100%)                                    
US$M       DATE                                                  
                                                                                
Petroleum                                                                       
Projects                                                                        
Neptune (US)    405        Mid CY08    50,000     First production              
35%                                    barrels of announced, see News           
Oil/Gas                                oil and 50 Release dated 6 July          
                                      million    2008.                          
cubic feet                                
                                      gas per                                   
                                      day                                       
North West      350        Late CY08   LNG        Start-up achieved ahead       
Shelf Train 5                          processing of schedule and on            
(Australia)                            capacity   budget.  See News Release     
16.67%                                 of 4.4     dated 1 September 2008.       
LNG                                    million                                  
tpa                                       
North West      200        End CY08    800        Start-up achieved ahead       
Shelf Angel                            million    of schedule and on            
(Australia)                            cubic feet budget. See News Release      
16.67%                                 gas per    dated 3 October 2008.         
Oil/Gas                                day and                                  
                                      50,000 bpd                                
                                      condensate                                
Shenzi (US)     1,940      Mid CY09    100,000    Ahead of schedule and on      
44%                                    barrels of budget. Subsea hook-up of     
Oil/Gas                                oil and 50 wells and commissioning       
                                      million    of topsides commenced.         
cubic feet Two of five wells              
                                      gas per    complete, with the third       
                                      day        and fourth wells nearing       
                                                 completion.                    
Atlantis North  185        H2 CY09     Tieback to On schedule and budget.       
(US)                                   Atlantis   Flowlines installed and       
44%                                    South      manifold fabrication          
Oil/Gas                                           continuing.                   

                                                                                
Pyrenees        1,200      H1 CY10     96,000     On schedule and budget.       
(Australia)                            barrels of Floating Production           
71.43%                                 oil and 60 Storage and Offtake           
Oil/Gas                                million    (FPSO) conversion             
                                      cubic feet continues.                     
                                      gas per                                   
day                                       
Angostura Gas   180        H1 CY11     280        On schedule and budget.       
Phase II                               million    The project was               
(Trinidad and                          cubic feet sanctioned during the         
Tobago)                                gas per    quarter. See News Release     
45%                                    day        dated 16 September 2008.      
Gas                                                                             
Bass Strait     500        CY11        10,000 bpd On schedule and budget.       
Kipper                                 condensate Line pipe delivered, with     
(Australia)                            and        engineering and               
32.5% - 50%                            processing procurement progressing.      
Gas/Gas                                capacity                                 
Liquids                                of 80                                    
                                      million                                   
                                      cubic feet                                
                                      gas per                                   
day                                       
Bass Strait     625        CY11        11,000 bpd On schedule and budget.       
Turrum                                 condensate The project was               
(Australia)                            and        sanctioned during the         
50%                                    processing quarter. See News Release     
Gas/Gas                                capacity   dated 25 July 2008.           
Liquids                                of 200                                   
                                      million                                   
cubic feet                                
                                      gas per                                   
                                      day                                       
North West      850        CY12        2,500      On schedule and budget.       
Shelf North                            million    Detailed engineering and      
Rankin B Gas                           cubic feet procurement progressing.      
Compression                            gas per                                  
(Australia)                            day                                      
16.67%                                                                          
LNG                                                                             
PROJECT AND     SHARE OF   INITIAL     PRODUCTION QUARTERLY PROGRESS            
OWNERSHIP       APPROVED   PRODUCTION  CAPACITY                                 
CAPEX      TARGET      (100%)                                    
               US$M       DATE                                                  
                                                                                
Minerals                                                                        
Projects                                                                        
Alumar -        900        Q2 CY09     2 million  On schedule with revised      
Refinery                               tpa of     budget. Budget revised        
Expansion                              alumina    due to foreign exchange       
(Brazil) 36%                                      and other industry cost       
Alumina                                           pressures which are in        
                                                 line with other major          
                                                 projects in Brazil.            
Engineering is complete        
                                                 and procurement well           
                                                 advanced. Construction is      
                                                 70% complete with the          
project overall 85%            
                                                 complete.                      
Worsley         1,900      H1 CY11     1.1        On schedule and budget.       
Efficiency &                           million    Major contracts for           
Growth                                 tpa of     precipitation,                
(Australia)                            alumina    structural, mechanical        
86%                                               and piping awarded. Site      
Alumina                                           works commenced.              
Iron Ore        1,850      H1 CY10     26 million On schedule and on budget     
(Western                               tpa        in local currency.            
Australia)                             additional Engineering is now over       
RGP4                                   iron ore   90% complete and              
86.2%                                  system     construction is 48%           
Iron Ore                               capacity   complete.                     
Gemco           110        H1 CY09     1 million  On schedule and budget in     
(Australia)                            tpa of     local currency. Project       
60%                                    additional civil construction is         
Manganese                              manganese  underway and procurement      
                                      concentrat activities progressing         
                                      e          well. Project is 65%           
complete.                      
Klipspruit      450        H2 CY09     Incrementa On schedule and budget.       
(South Africa)                         l 1.8      Engineering significantly     
100%                                   million    advanced with civil and       
Energy Coal                            tpa export plant erection works          
                                      thermal    progressing well. Project      
                                      coal       is over 50% complete.          
                                      Incrementa                                
l 2.1                                     
                                      million                                   
                                      tpa                                       
                                      domestic                                  
thermal                                   
                                      coal                                      
Douglas-        975        Mid CY10    10 million On schedule and budget.       
Middelburg                             tpa export Earthworks and civil          
Optimisation                           thermal    engineering are well          
(South Africa)                         coal and   advanced and steel            
100%                                   8.5        fabrication is                
Energy Coal                            million    progressing as scheduled.     
tpa        All long lead time items       
                                      domestic   ordered.                       
                                      thermal                                   
                                      coal                                      
(sustains                                 
                                      current                                   
                                      output)                                   
Newcastle       390        CY10        Export     On schedule and budget.       
Third Port                             coal       Project is over 20%           
Project                                loading    complete.                     
(Australia)                            facility                                 
35.5%                                  30 million                               
Energy Coal                            tpa                                      
MINERALS EXPLORATION                                                            
BHP Billiton remains committed to invest in our future through the pursuit of   
global exploration opportunities for key commodities of interest utilising both 
in-house capabilities and partnerships.                                         
Grassroots exploration continued on copper targets in Australia, Chile,         
Argentina and the Democratic Republic of Congo (DRC); on nickel targets in      
Australia, Russia, Colombia and Africa and on diamond targets in the DRC and    
Canada. Exploration for iron ore, coal, bauxite and manganese was undertaken in 
a number of regions including Australia, South America, Russia and West Africa. 
For the quarter ended 30 September 2008, BHP Billiton spent US$166 million on   
minerals exploration, of which US$146 million was expensed.                     
PETROLEUM EXPLORATION                                                           
Exploration and appraisal wells drilled during the quarter or in the process of 
drilling as at 30 September 2008.                                               
WELL             LOCATION         BHP BILLITON EQUITY STATUS                    
Calliance-3      Browse Basin     20% BHP Billiton    Hydrocarbons              
                Western          (Woodside operator) encountered.               
                Australia                            Well suspended.            
                WA-28-R                                                         
Lambert-8        Dampier Sub-     16.67% BHP Billiton Drilling ahead.           
                Basin            (Woodside operator)                            
                Western                                                         
                Australia                                                       
WA-16-L                                                         
Shenzi-81        Green Canyon     44% BHP Billiton    Drilling ahead.           
                Gulf of Mexico   operator                                       
                GC610                                                           
Petroleum exploration expenditure for the quarter ended 30 September 2008 was   
US$148 million, of which US$107 million was expensed.                           
1    Shenzi-8 is the replacement well for Shenzi-7, which was plugged and       
    abandoned after encountering mechanical difficulties in the top-hole        
section.                                                                    
Further information on BHP Billiton can be found on our Internet site:          
www.bhpbilliton.com                                                             
Australia                                                                       
Samantha Evans, Media Relations                                                 
Tel: +61 3 9609 2898 Mobile: +61 400 693 915                                    
email: Samantha.Evans@bhpbilliton.com                                           
Peter Ogden Evans, Media Relations                                              
Tel: +61 3 9609 2812 Mobile: +61 428 599 190                                    
email: Peter.Ogden@bhpbilliton.com                                              
Leng Lau, Investor Relations                                                    
Tel: +61 3 9609 4202 Mobile: +61 403 533 706                                    
email: Leng.Y.Lau@bhpbilliton.com                                               
United Kingdom & South Africa                                                   
Andre Liebenberg, Investor Relations                                            
Tel: +44 20 7802 4131 Mobile: +44 7920 236 974                                  
email: Andre.Liebenberg@bhpbilliton.com                                         
Illtud Harri, Media Relations                                                   
Tel: +44 20 7802 4195 Mobile: +44 7920 237 246                                  
email: Illtud.Harri@bhpbilliton.com                                             
United States                                                                   
Scott Espenshade, Investor Relations                                            
Tel: +1 713 599 6431 Mobile: +1 713 208 8565                                    
email: Scott.Espenshade@bhpbilliton.com                                         
Ruban Yogarajah, Media Relations                                                
Tel: US +1 713 966 2907 Mobile: UK +44 20 7802 4033                             
Mobile: UK +44 7827 082 022                                                     
email: Ruban.Yogarajah@bhpbilliton.com                                          
BHP Billiton Limited ABN 49 004 028 077                                         
Registered in Australia                                                         
Registered Office:                                                              
Level 27, 180 Lonsdale Street Melbourne Victoria 3000                           
Telephone +61 1300 554 757                                                      
Facsimile +61 3 9609 3015                                                       
BHP Billiton Plc Registration number 3196209                                    
Registered in England and Wales                                                 
Registered Office: Neathouse Place London SW1V 1BH United Kingdom               
Telephone +44 20 7802 4000                                                      
Facsimile +44 20 7802 4111                                                      
The BHP Billiton Group is headquartered in Australia                            
Date: 22/10/2008 08:03:11 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.