BIL - BHP Billiton Plc - News Release12 Jun 2008
BIL
BIBLT                                                                           
BIL - BHP Billiton Plc - News Release                                           
BHP Billiton Plc                                                                
Share code: BIL                                                                 
ISIN: GB0000566504                                                              
NEWS RELEASE                                                                    
Date: 12 June 2008                                                              
BHP BILLITON TO IMMEDIATELY COMMENCE A FURNACE REBUILD AT KALGOORLIE NICKEL     
SMELTER                                                                         
BHP Billiton today announced that, as a result of a deterioration of the        
Kalgoorlie Nickel Smelter furnace in Western Australia, it would bring          
forward the furnace rebuild.                                                    
Planning and preparation for a major rebuild of the furnace has been in         
progress for the past two years.  The rebuild was planned to occur later in     
the next financial year, however an assessment of the furnace condition has     
determined the rebuild must take place now to ensure the ongoing safety of      
the workplace.                                                                  
The duration of the rebuild is estimated to be around four months.              
The Kalgoorlie Nickel Smelter normally produces around 100,000 tonnes of        
nickel-in-matte per annum that is both the feedstock for the Kwinana Nickel     
Refinery and exported to international customers. The estimated impact on       
sales in the 2009 financial year is expected to be around 25,000 tonnes of      
contained nickel units, plus 3,000 tonnes of contained nickel units in the      
2008 financial year.                                                            
As a result of the furnace rebuild the Kwinana Nickel Refinery will be forced   
to shutdown for the duration of the rebuild. The shutdown will commence         
immediately. BHP Billiton`s Nickel West operations are endeavouring to          
continue concentrate production.                                                
As a consequence of the furnace rebuild, BHP Billiton is reallocating gas to    
the Worsley Alumina Refinery.                                                   
Further information on BHP Billiton can be found on our Internet site:          
www.bhpbilliton.com                                                             
Australia                      United Kingdom & South Africa                    
Samantha Evans, Media          Andre Liebenberg, Investor                       
Relations                      Relations                                        
Tel: +61 3 9609 2898  Mobile:  Tel: +44 20 7802 4131                            
+61 400 693 915                Mobile: +44 7920 236 974                         
email:                         email:                                           
Samantha.Evans@bhpbilliton.co  Andre.Liebenberg@bhpbilliton.                    
m                              com                                              

Leng Lau, Investor Relations   Illtud Harri, Media Relations                    
Tel: +61 3 9609 4202  Mobile:  Tel: +44 20 7802 4195                            
+61 403 533 706                Mobile: +44 7920 237 246                         
email:                         email:                                           
Leng.Y.Lau@bhpbilliton.com     Illtud.Harri@bhpbilliton.com                     
                                                                                
United States                                                                   
Tracey Whitehead, Investor &                                                    
Media Relations                                                                 
Tel: US +1 713 599 6100 or UK                                                   
+44 20 7802 4031                                                                
Mobile: +44 7917 648 093                                                        
email:                                                                          
Tracey.Whitehead@bhpbilliton.                                                   
com                                                                             
Date: 12/06/2008 07:07:01 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.