BIL - BHP Billiton Plc - Quarterly Report On Explo23 Oct 2007
BIL
 BIBLT                                                                           
BIL - BHP Billiton Plc - Quarterly Report On Exploration And Development        
                        Activities Quarter Ended 30 September 2007              
BHP Billiton Plc                                                                
Share code:  BIL                                                                
ISIN: GB0000566504                                                              
23 October 2007                                                                 
Number 31/07                                                                    
BHP BILLITON QUARTERLY REPORT ON EXPLORATION AND DEVELOPMENT ACTIVITIES         
QUARTER ENDED 30 SEPTEMBER 2007                                                 
This report covers the company`s exploration and development activities for the 
quarter ended 30 September 2007. This report together with the Production Report
represents the Interim Management Statement for the purposes of the UK Listing  
Authority`s Disclosure and Transparency Rules. There have been no significant   
changes in the financial position of the Group in the quarter ended 30 September
2007. Unless otherwise stated, BHP Billiton`s interest in the projects referred 
to in this report is 100 per cent and references to project schedules are based 
on calendar years.                                                              
DEVELOPMENT                                                                     
In October, oil production commenced at the Genghis Khan and Atlantis fields in 
the Gulf of Mexico. These projects will not be reported in future Exploration   
and Development Reports.                                                        
PROJECT AND     SHARE OF   INITIAL    PRODUCTION  QUARTERLY PROGRESS            
OWNERSHIP       APPROVED   PRODUCTIO  CAPACITY                                  
CAPEX      N TARGET   (100%)                                     
               US$M       DATE                                                  
                                                                                
Petroleum                                                                       
Projects                                                                        
Genghis Khan    365        2H CY07    55,000      First well was completed      
(US)                                  barrels of  during the quarter. First     
44%                                   oil per day oil announced, see            
Oil/Gas                                           News@BHPBilliton dated 8      
                                                 October 2007.                  
Atlantis South  1,630      2H CY07    200,000     On schedule and on            
(US)                                  barrels of  revised budget.  Nine         
44%                                   oil and 180 production wells have         
Oil/Gas                               million     been drilled and seven        
                                     cubic feet  completed. The first well      
                                     of gas per  is online and the field        
day         will begin ramping up oil      
                                                 and gas production             
                                                 towards the end of this        
                                                 calendar year.                 
Neptune (US)    405        Q1 CY08    50,000      On revised budget, and        
35%                                   barrels of  schedule moved to Q1          
Oil/Gas                               oil and 50  CY08. Offshore hookup and     
                                     million     commissioning of               
cubic feet  pipelines and topsides         
                                     gas per day continued.  Four of seven      
                                                 wells have been drilled        
                                                 with two completed.            
Stybarrow       380        End CY07   80,000      On revised budget and         
(Australia)                           barrels of  schedule moved forward to     
50%                                   oil per day end CY07. Three of five       
Oil/Gas                                           producing wells and all       
injector wells have been       
                                                 drilled and completed.         
                                                 FPSO now on location and       
                                                 installation of subsea         
equipment continued.           
PROJECT AND     SHARE OF   INITIAL    PRODUCTION  QUARTERLY PROGRESS            
OWNERSHIP       APPROVED   PRODUCTIO  CAPACITY                                  
               CAPEX      N TARGET   (100%)                                     
US$M       DATE                                                  
                                                                                
Petroleum                                                                       
Projects                                                                        
North West      200        End CY08   800 million On schedule and budget.       
Shelf Angel                           cubic feet  Topsides fabrication          
(Australia)                           gas per day continued.  Jacket            
16.67%                                            completed and loaded out      
Oil/Gas                                           ready for sail away.          
North West      350        Late CY08  LNG         On schedule and revised       
Shelf Train 5                         processing  budget as advised by the      
(Australia)                           capacity of Operator. Onsite              
16.67%                                4.2 million construction and hookup       
LNG                                   tpa         progressing.                  
Shenzi (US)     1,940      Mid CY09   100,000     On schedule and budget.       
44%                                   barrels of  Hull and topsides             
Oil/Gas                               oil and 50  fabrication continues.        
                                     million     The top section on the         
                                     cubic feet  third of six development       
                                     gas per day wells was drilled.             
Pyrenees        1,200      1H CY10    96,000      On schedule and budget.       
(Australia)                           barrels of  FPSO with 9 producing         
71.43%                                oil and 60  wells and 4 injection         
Oil/Gas                               million     wells in 200m water           
cubic feet  depth. Contracts for           
                                     gas per day FPSO, subsea components        
                                                 and installation signed.       
                                                                                
Minerals                                                                        
Projects                                                                        
Alumar -        725        Q2 CY09    2 million   On revised schedule and       
Refinery                              tpa         budget, project is 56%        
Expansion                                         complete. Detailed            
(Brazil)                                          engineering is nearing        
36%                                               completion, with              
Alumina                                           procurement and               
construction progressing.      
Pinto Valley    140        Q4 CY07    70,000 tpa  On schedule and budget.       
Restart (USA)                         Copper in   Construction is 98%           
100%                                  concentrate complete.  Commissioning      
Copper                                            of the concentrator has       
                                                 commenced.                     
                                                                                
Koala           200        End CY07   3,300       First kimberlite              
Underground                           tonnes per  production blast during       
(Canada)                              day ore     October. Ahead of             
80%                                   processed   schedule and within           
Diamonds                                          budget.                       
Ravensthorpe    2,200      Q1 CY08    Up to       On revised schedule and       
(Australia)                           50,000 tpa  budget.  Construction and     
100%                                  contained   pre-commissioning are         
Nickel                                nickel in   essentially complete with     
concentrate only 10% wet                   
                                                 commissioning remaining.       
                                                 Process commissioning of       
                                                 the plant has commenced        
and is progressing to          
                                                 schedule.                      
                                                 Utilities are advanced         
                                                 with beneficiation and         
atmospheric leach in           
                                                 early stages of                
                                                 commissioning.                 
                                                 The first Pressure Acid        
Leach circuit is ready to      
                                                 commence process               
                                                 commissioning.                 
PROJECT AND     SHARE OF   INITIAL     PRODUCTION QUARTERLY PROGRESS            
OWNERSHIP       APPROVED   PRODUCTION  CAPACITY                                 
               CAPEX      TARGET      (100%)                                    
               US$M       DATE                                                  
                                                                                
Minerals                                                                        
Projects                                                                        
Yabulu          556        Q1 CY08     45,000 tpa On revised schedule and       
(Australia)                            nickel     budget. The Yabulu            
100%                                              Expansion is mechanically     
Nickel                                            complete and                  
                                                 commissioned. Ramp up          
                                                 will commence with the         
delivery of feed from          
                                                 Ravensthorpe.                  
Cliffs Nickel   139        1H CY08     360,000    On schedule and budget.       
Project                                tpa nickel Total project progress        
100%                                   ore        15% complete. Major           
Nickel                                            activities in the current     
                                                 quarter included work on       
                                                 ventilation shafts,            
underground development        
                                                 and earthworks.                
Iron Ore        1,300      Q4 CY07     20 million On schedule and budget.       
(Western                               tpa        Engineering and               
Australia)                                        procurement activities        
RGP3                                              are complete, with            
85%                                               construction activities       
Iron Ore                                          now 85% complete.             
Commissioning activities       
                                                 have commenced.                
Iron Ore        1,850      1H CY10     26 million On schedule and budget.       
(Western                               tpa        Engineering progress is       
Australia)                                        now over 50% complete         
RGP4                                              with procurement work         
86.2%                                             continuing. Earthwork         
Iron Ore                                          contractors are mobilised     
at all sites.                  
Samarco Third   590        1H CY08     7.6        On schedule and budget.       
Pellet Plant                           million    Total project progress is     
(Brazil)                               tpa        86% complete.                 
50%                                                                             
Iron Ore                                                                        
MINERALS EXPLORATION                                                            
BHP Billiton continued to pursue global exploration opportunities for key       
commodities of interest utilising both in-house capabilities and partnerships.  
Grassroots exploration continued on diamond targets in Angola and the Democratic
Republic of Congo (DRC), on copper targets in Australia, Chile, Mongolia, the   
DRC and Kazakhstan; and on nickel targets in Australia, Brazil and Africa,      
including Burundi and Tanzania.  Exploration for iron ore, coal, potash and     
bauxite was undertaken in a number of regions including Australia, South        
America, Canada and West Africa. Brownfield exploration continued around        
existing operations.                                                            
For the three months ended 30 September 2007, BHP Billiton spent US$143 million 
on minerals exploration of which US$109 million was expensed.                   
PETROLEUM EXPLORATION                                                           
Exploration and appraisal wells drilled during the quarter or in the process of 
drilling as at 30 September 2007.                                               
WELL              LOCATION        BHP BILLITON EQUITY STATUS                    
Big Foot North-1  Green Canyon    55% BHP Billiton    Drilling suspended.       
                 Gulf of Mexico  and operator        Waiting on rig to          
GC-953                              continue drilling.         
Kugler-1          Trinidad &      25.5% BHP Billiton  Hydrocarbons              
                 Tobago          (Anadarko operator) encountered. Plugged       
                 Block 3(b)                          and abandoned.             
Kairi Horst (KAI- Trinidad &      45% BHP Billiton    Hydrocarbons              
B12)              Tobago          and operator        encountered.              
                 Block 2(c)                          Well completed.            
Thebe-1           Exmouth         100% BHP Billiton   Encountered               
Plateau         and operator        approximately 240          
                 Western                             feet of gas column.        
                 Australia                           Additional appraisal       
                 WA-346-P                            required.                  
Plugged and                
                                                     abandoned.                 
                                                     See News@BHPBilliton       
                                                     dated 13 August 2007.      
Torosa-4          Browse Basin    8.33% BHP Billiton  Drilling suspended.       
                 Western         (Woodside operator) Waiting on rig to          
                 Australia                           continue drilling.         
                 WA-30-R                                                        
Snarf -1          Browse Basin    20% BHP Billiton    Drilling suspended.       
                 Western         (Woodside operator) Waiting on rig to          
                 Australia                           continue drilling.         
                 WA-275-P                                                       
Lady Nora-1       Carnarvon       16.67% BHP Billiton Hydrocarbons              
                 Basin           (Woodside operator) encountered. Plugged       
                 Western                             and abandoned.             
                 Australia                                                      
WA-28-P                                                        
Glenridding-1     Exmouth sub-    50% BHP Billiton    Dry hole. Plugged and     
                 basin           and operator        abandoned.                 
                 Western                                                        
Australia                                                      
                 WA-32-L                                                        
Petroleum exploration expenditure for the three months ended 30 September 2007  
was US$124 million of which US$72 million was expensed.                         
Further information on BHP Billiton can be found on our Internet site:          
www.bhpbilliton.com                                                             
Australia                                                                       
Samantha Evans, Media Relations                                                 
Tel: +61 3 9609 2898  Mobile: +61 400 693 915                                   
email: Samantha.Evans@bhpbilliton.com                                           
Jane Belcher, Investor Relations                                                
Tel: +61 3 9609 3952  Mobile: +61 417 031 653                                   
email: Jane.H.Belcher@bhpbilliton.com                                           
United Kingdom                                                                  
Andre Liebenberg, Investor Relations                                            
Tel: +44 20 7802 4131  Mobile: +44 7920 236 974                                 
email: Andre.Liebenberg@bhpbilliton.com                                         
Illtud Harri, Media Relations                                                   
Tel: +44 20 7802 4195  Mobile: +44 7920 237 246                                 
email: Illtud.Harri@bhpbilliton.com                                             
United States                                                                   
Tracey Whitehead, Investor & Media Relations                                    
Tel: US +1 713 599 6100 or UK +44 20 7802 4031                                  
Mobile: +44 7917 648 093                                                        
email: Tracey.Whitehead@bhpbilliton.com                                         
South Africa                                                                    
Alison Gilbert, Investor Relations                                              
Tel: SA +27 11 376 2121 or UK +44 20 7802 4183                                  
Mobile: +44 7769 936 227                                                        
email: Alison.Gilbert@bhpbilliton.com                                           
Date: 23/10/2007 07:26:45 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.