GBG - Great Basin Gold Limited - Great Basin annou12 Jul 2010
GBG
GBG                                                                             
GBG - Great Basin Gold Limited - Great Basin announces Burnstone Project update 
site to receive Eskom power on August 8, 2010                                   
GREAT BASIN GOLD LIMITED                                                        
(Incorporated in Canada and registered as an External Company in South Africa)  
(Registration No. 2006/021304/10)                                               
Share Code: GBG      ISIN Number: CA3901241057                                  
("Great Basin Gold" or "the Company")                                           
GREAT BASIN ANNOUNCES BURNSTONE PROJECT UPDATE SITE TO RECEIVE ESKOM POWER ON   
AUGUST 8, 2010                                                                  
July 12, 2010, Vancouver, BC - Great Basin Gold Ltd. ("Great Basin" or the      
"Company") (TSX: GBG; NYSE Amex: GBG; JSE: GBG) announces progress in the       
delivery of the capital projects at its Burnstone Mine development project in   
South Africa.                                                                   
Eskom, the state energy provider, has informed the Company that final           
arrangements have been made to tie the Burnstone project in to the national     
electricity grid on August 8, 2010, which is a delay of approximately 2 weeks   
with a resultant delay in plant start up.  The establishment of bulk electrical 
power infrastructure to the Burnstone Mine by Eskom is well advanced. The main  
distribution substation at Burnstone site is complete and the receiving         
infrastructure being part of the Eskom line project is ready to receive         
electrical power.  Power supply to Burnstone is enabled through the execution of
a two phased project, with phase 1 the delivery of a single line, designed to   
carry the full demand (51 megavolt-amperes (MVA), scaled from 21 MVA initially  
and building up to the full requirement as production builds up. Phase 2 is the 
construction of a second, identical, line with the aim of mitigating the risk of
power outages to the mine and region.  This second line will not increase the   
capacity of the supply, but is aimed at security of supply, commensurate with   
Eskom`s risk and safety policies.                                               
To date, the metallurgical plant construction project has made rapid progress   
against an aggressive 15 month delivery time line. The project thus far has seen
intensive civil construction activities on-site and a multitude of simultaneous 
assembly and refurbishment activities off site. The heavy civil construction has
largely been completed, construction of various buildings is far advanced, and  
the off-site assembled components are being delivered and installed.            
Over the past month, the ball and semi autogenous grinding mill shells and heads
have been mounted in position, the mill motors have been installed and general  
alignment and installation procedures completed.  Currently the lubrication     
systems and mill liners are being installed.                                    
The silo is in its final stage of completion with the roof steel installed and  
the final associated civil construction being finalised.  Installation of steel 
feeder systems at the silo bottom is in progress.                               
The main feed conveyor gantries have also been assembled and are being          
installed.                                                                      
The thickener installation is complete and a final layer of paint is being      
applied.  The installation of the flocculent plant and the construction of      
process tanks for start-up have also been completed.                            
All sub-station and central buildings are complete and electrical and           
instrumentation installation is in progress.  Piping and cable racking          
construction is far advanced and installation of pipes, cables, pumps and       
associated components are in progress.  The cable trenching and installation    
from the main Eskom sub-station is complete and ready to receive power.         
The tailings facility project is progressing well, with Phase 1 having been     
completed and ready to receive tailings from the plant.  A water storage and    
supply dam has been activated with surplus underground water being pumped into  
and stored in it.  Upon commissioning, the raw water storage and thickener tanks
in the metallurgical plant will be filled as well.                              
Another highlight in the past two months was completion of the sinking phase of 
the Burnstone vertical shaft to its final depth of 1,598 ft (487 m) on May 4,   
2010. In addition, the initial development on 40 Level and 41 Level Stations    
were completed.  A conveyor system required for ore handling has been installed 
on 41 Level.  Equipping of the shaft continues and is expected to be completed  
in August 2010. The winder house construction has been completed; both winders  
were dry commissioned at the end of last week, and ahead of schedule.           
The holing of the 5.1-m diameter, 305-m deep vertical ventilation shaft took    
place on May 12, 2010 and will act as an up-cast shaft to provide sufficient    
ventilation for mining of blocks B and C.  The lining of the first 90 m of the  
shaft with shotcrete as well as connection of three 720 kiloWatt surface fans is
in progress.  The shaft will provide adequate ventilation for the underground   
workings well into the future.                                                  
Good progress also continues to be made in the development of underground       
infrastructure at Burnstone.  A significant milestone was achieved on June 24   
with the holing of the decline with the vertical shaft.  A total of 8,822 ft    
(2,692 m) of on-reef development was completed by the end of June 2010.  The    
long hole stoping trials are progressing well and the rate of mining is expected
to increase as more mining areas become available. The focus is on establishing 
more stopes in Block B while activities in the higher grade Block C continue to 
be focused on reef development. Block C Middle level was accessed during the    
previous quarter with Block C Upper scheduled to be accessed in July 2010. The  
additional access points in Block C will allow for an increase in opening up of 
new mining areas. A total of approximately 126,000 tons have been accumulated on
the ore stockpiles which will be used for mill commissioning.                   
Ferdi Dippenaar, President and CEO, commented: "Although delayed, finalization  
of the power supply from Eskom is a significant step towards the commissioning  
of the Burnstone metallurgical plant. Internal delays at Eskom impacted on its  
previous commitments to deliver power to site by the end of June 2010.          
Fortunately, the delay in commissioning the mill is only limited to two weeks,  
and is not expected to significantly impact on the planned ore throughput."     
Johan Oelofse, Pr.Eng., FSAIMM, Chief Operating Officer of Great Basin and a    
qualified person, as defined by Canadian regulatory policy, has reviewed and    
assumed responsibility for the technical information contained in this release. 
For additional details on Great Basin and its gold properties, please visit the 
Company`s website at www.grtbasin.com or contact Investor Services:             
         Tsholo Serunye in South Africa                27 (0) 11 301 1800       
         Michael Curlook in North America            1 (888) 633 9332           
         Barbara Cano at Breakstone Group in the USA         (646) 452 2334     
No regulatory authority has approved or disapproved the information    
         contained in this news release.                                        
Cautionary and Forward Looking Statement Information                            
This document contains "forward-looking statements" that were based on Great    
Basin`s expectations, estimates and projections as of the dates as of which     
those statements were made. Generally, these forward-looking statements can be  
identified by the use of forward-looking terminology such as "outlook",         
"anticipate", "project", "target", "believe", "estimate", "expect", "intend",   
"should" and similar expressions. Forward-looking statements are subject to     
known and unknown risks, uncertainties and other factors that may cause the     
Company`s actual results, level of activity, performance or achievements to be  
materially different from those expressed or implied by such forward-looking    
statements. These include but are not limited to:                               
*    uncertainties and costs related to the Company`s exploration and           
    development activities, such as those associated with determining whether   
    mineral resources or reserves exist on a property;                          
*    uncertainties related to feasibility studies that provide estimates of     
    expected or anticipated costs, expenditures and economic returns from a     
    mining project; uncertainties related to expected production rates, timing  
    of production and the cash and total costs of production and milling;       
*    uncertainties related to the ability to obtain necessary licenses, permits,
    electricity, surface rights and title for development projects;             
*    operating and technical difficulties in connection with mining development 
    activities;                                                                 
*    uncertainties related to the accuracy of our mineral reserve and mineral   
    resource estimates and our estimates of future production and future cash   
    and total costs of production, and the geotechnical or hydrogeological      
    nature of ore deposits, and diminishing quantities or grades of mineral     
reserves;                                                                   
*    uncertainties related to unexpected judicial or regulatory proceedings;    
*    changes in, and the effects of, the laws, regulations and government       
    policies affecting our mining operations, particularly laws, regulations    
and policies relating to                                                    
*    mine expansions, environmental protection and associated compliance costs  
    arising from exploration, mine development, mine operations and mine        
    closures;                                                                   
*    expected effective future tax rates in jurisdictions in which our          
    operations are located;                                                     
*    the protection of the health and safety of mine workers; and               
*    mineral rights ownership in countries where our mineral deposits are       
located, including the effect of the Mineral and Petroleum Resources        
    Development Act (South Africa);                                             
*    changes in general economic conditions, the financial markets and in the   
    demand and market price for gold, silver and other minerals and             
commodities, such as diesel fuel, coal, petroleum coke, steel, concrete,    
    electricity and other forms of energy, mining equipment, and fluctuations   
    in exchange rates, particularly with respect to the value of the U.S.       
    dollar, Canadian dollar and South African rand;                             
*    unusual or unexpected formation, cave-ins, flooding, pressures, and        
    precious metals losses (and the risk of inadequate insurance or inability   
    to obtain insurance to cover these risks);                                  
*    changes in accounting policies and methods we use to report our financial  
condition, including uncertainties associated with critical accounting      
    assumptions and estimates;                                                  
*    environmental issues and liabilities associated with mining including      
    processing and stock piling ore;                                            
*    geopolitical uncertainty and political and economic instability in         
    countries which we operate;  and                                            
*    labour strikes, work stoppages, or other interruptions to, or difficulties 
    in, the employment of labour in markets in which we operate mines, or       
environmental hazards, industrial accidents or other events or occurrences, 
    including third party interference that interrupt the production of         
    minerals in our mines.                                                      
For further information on Great Basin Gold, investors should review the        
Company`s annual Form 40-F filing with the United States Securities and Exchange
Commission www.sec.com and home jurisdiction filings that are available at      
www.sedar.com.                                                                  
12 July 2010                                                                    
Sponsor                                                                         
Nedbank Capital                                                                 
Date: 12/07/2010 14:30:01 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.