GBG - Great Basin - Great Basin Provides Update On2 Jun 2010
GBG
GBG                                                                             
GBG - Great Basin - Great Basin Provides Update On Burnstone Mine Project       
GREAT BASIN GOLD LIMITED                                                        
(Incorporated in Canada and registered as an External Company in South Africa)  
(Registration No. 2006/021304/10)                                               
Share Code: GBG & ISIN Number: CA3901241057                                     
("Great Basin" or "the Company")                                                
GREAT BASIN PROVIDES UPDATE ON BURNSTONE MINE PROJECT                           
June 2, 2010, Vancouver, BC - Great Basin Gold Ltd. ("Great Basin" or the       
"Company") (TSX: GBG; NYSE Amex: GBG; JSE: GBG) announces that it is making good
progress in the delivery of its capital projects at its Burnstone Project in    
South Africa.                                                                   
To date, the metallurgical plant construction project has made rapid progress   
against an aggressive 15 month delivery time line. The project thus far has seen
intensive civil construction activities on-site and a multitude of simultaneous 
assembly and refurbishment activities off site.  The project is now entering the
stage where the heavy civil construction has largely been completed,            
construction of various buildings is far advanced, and the off-site assembled   
components are being delivered and installed.                                   
Over the past month, the ball and semi autogenous grinding mill shells and heads
have been mounted in position, the pour of the 2 meter thick slab floor for the 
silo has been completed, the cable racks and piping has started on the main pipe
racks, the cable trenching from the Eskom sub-station has been completed and is 
ready to receive power, the construction of the Carbon-in-Leach tanks and       
thickener has progressed to an advanced state.                                  
The tailings facility project is progressing well, and will be ready to coincide
with commissioning of the plant.                                                
Progress at the vertical shaft project is aimed at completing shaft bottom      
arrangements, in order to continue with shaft equipping and commissioning. The  
winder house construction has been completed and both winders are in an advanced
stage of installation, ahead of schedule.                                       
The establishment of bulk electrical power to the Burnstone Mine is ongoing and 
construction of the power line is progressing according to plan.  Eskom remains 
committed to supply the Burnstone Mine with bulk electrical power as per the    
agreed schedule and according to the power demand build-up.  The main           
distribution substation at the Burnstone site is almost complete with the last  
switchgear being installed this week and the receiving infrastructure being due 
for completion as part of the Eskom line project.                               
The Burnstone Project has achieved a major milestone by effective compliance    
with the compulsory 10% power savings initiative from Eskom, by the submission  
of an "Energy Efficiency Certificate", indicating energy efficient designs and  
components that are acknowledged by Eskom.  This arrangement, a first according 
to Eskom, and aligned with its forward looking energy saving policies, will     
effectively avoid the punitive rates for not achieving the compulsory 10%       
savings.                                                                        
Ferdi Dippenaar, President and CEO, commented: "As at May 30, 2010, the decline 
had progressed to within 20 meters of the vertical shaft, with the breakthrough 
planned in the week of June 10, following the completion of shaft equipping on  
shaft bottom and 41 Level Station.   Approximately 2,130 meters of underground  
on-reef development meters have been completed with Long Hole Stoping trials    
continuing during May 2010.  The project team at our Burnstone operation        
continues to make good progress in delivering these strategically important     
projects that, combined with the underground development and opening up of      
production areas, form the critical path to delivery of the Burnstone Mine by   
the end of June 2010."                                                          
Johan Oelofse, Pr.Eng., FSAIMM, Chief Operating Officer of Great Basin and a    
qualified person, as defined by Canadian regulatory policy, has reviewed and    
assumed responsibility for the technical information contained in this release. 
For additional details on Great Basin and its gold properties, please visit the 
Company`s website at www.grtbasin.com or contact Investor Services:             
Tsholo Serunye in South Africa                27 (0) 11 301 1800                
Michael Curlook in North America            1 (888) 633 9332                    
Barbara Cano at Breakstone Group in the USA         (646) 452 2334              
No regulatory authority has approved or disapproved the information contained in
this news release.                                                              
This release includes certain statements that may be deemed "forward-looking    
statements". All statements in this release, other than statements of historical
facts, that address possible future commercial production, reserve potential,   
exploration drilling results, development, feasibility or exploitation          
activities and events or developments that Great Basin Gold expects to occur are
forward-looking statements. Although the Company believes the expectations      
expressed in such forward-looking statements are based on reasonable            
assumptions, such statements are not guarantees of future performance and actual
results or developments may differ materially from those in the forward-looking 
statements. Factors that could cause actual results to differ materially from   
those in forward-looking statements include market prices, exploitation and     
exploration successes, continuity of mineralization, uncertainties related  to  
the ability to obtain necessary permits, licenses and title and delays due to   
third party opposition, geopolitical uncertainty, changes in government policies
regarding mining and natural resource exploration and exploitation, and         
continued availability of capital and financing, and general economic, market or
business conditions. Investors are cautioned that any such statements are not   
guarantees of future performance and those actual results or developments may   
differ materially from those projected in the forward-looking statements. For   
more information on the Company, Investors should review the Company`s annual   
Form 40-F filing with the United States Securities and Exchange Commission and  
its home jurisdiction filings that are available at www.sedar.com.              
Sponsor                                                                         
Nedbank Capital                                                                 
2 June 2010                                                                     
Date: 02/06/2010 16:21:03 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.